A drone captures a bird's eye view of an Underslung Temporary Beam (UTB) being used to place segments to form a viaduct over the Warragamba pipeline north of the Luddenham Station site on the new Sydney Metro - Western Sydney Airport line. Three viaduct structures make up the combined 3.5-kilometre section of the alignment that will take metro services over key locations including the Warragamba pipeline, Blaxland Creek and Luddenham Road. More than 1100 segments have been manufactured on the NSW Centra
Sydney Metro – Western Sydney Airport’s has just reached a massive milestone!
The viaduct has now been constructed over the Warragamba pipelines, which are the two pipelines responsible for transferring 80 percent of Sydney’s water from Warragamba Dam to filtration plants for treatment.
The 3.5 kilometre viaduct, which will connect

A drone captures a bird’s eye view of an Underslung Temporary Beam (UTB) being used to place segments to form a viaduct over the Warragamba pipeline north of the Luddenham Station site on the new Sydney Metro – Western Sydney Airport line.
Three viaduct structures make up the combined 3.5-kilometre section of the alignment that will take metro services over key locations including the Warragamba pipeline, Blaxland Creek and Luddenham Road.
More than 1100 segments have been manufactured on the NSW Centra
A drone captures a bird’s eye view of an Underslung Temporary Beam (UTB) being used to place segments to form a viaduct over the Warragamba pipeline north of the Luddenham Station site on the new Sydney Metro – Western Sydney Airport line.
Three viaduct structures make up the combined 3.5-kilometre section of the alignment that will take metro services over key locations including the Warragamba pipeline, Blaxland Creek and Luddenham Road.
More than 1100 segments have been manufactured on the NSW Centra
A drone captures a bird’s eye view of an Underslung Temporary Beam (UTB) being used to place segments to form a viaduct over the Warragamba pipeline north of the Luddenham Station site on the new Sydney Metro – Western Sydney Airport line.
Three viaduct structures make up the combined 3.5-kilometre section of the alignment that will take metro services over key locations including the Warragamba pipeline, Blaxland Creek and Luddenham Road.
More than 1100 segments have been manufactured on the NSW Centra
A drone captures a bird’s eye view of an Underslung Temporary Beam (UTB) being used to place segments to form a viaduct over the Warragamba pipeline north of the Luddenham Station site on the new Sydney Metro – Western Sydney Airport line.
Three viaduct structures make up the combined 3.5-kilometre section of the alignment that will take metro services over key locations including the Warragamba pipeline, Blaxland Creek and Luddenham Road.
More than 1100 segments have been manufactured on the NSW Centra

, is more than 80 percent complete.


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Leave a Reply

Your email address will not be published. Required fields are marked *

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading