Kenny Constructions’ recent progress on the M12 West project where they are completing FRP works for Bridges 1, 2 and 5.
Bridges 1 and 2 are approaching the final stages of completion with only the approach slabs and movement joints remaining. Bridge 5 is also progressing well with all the substructure now complete.