The Orchard Hills site continues to progress, with significant structural milestones achieved.
Recent Milestones:
✅ Piling works completed – 128 piles installed
✅ Main base slab finished – 11 concrete pours completed at the bottom of the station box
✅ Waterproofing installed – base slab and perimeter walls protected
✅ Suspended slab works underway – first pour completed
Structural Reinforcements:
On both sides of the station box, 22 perimeter wall pours have been completed, further strengthening the structure.
🔹 4,500+ tonnes of reinforcement installed
🔹 15,000m³+ of concrete poured, including:
- 6,500m³ for base slabs
- 3,500m³ for perimeter walls
The site continues to evolve as key structural elements take shape. Further updates to follow!


Discover more from Possession Planning
Subscribe to get the latest posts sent to your email.