The Orchard Hills site continues to progress, with significant structural milestones achieved.

Recent Milestones:

Piling works completed – 128 piles installed
Main base slab finished – 11 concrete pours completed at the bottom of the station box
Waterproofing installed – base slab and perimeter walls protected
Suspended slab works underway – first pour completed

Structural Reinforcements:

On both sides of the station box, 22 perimeter wall pours have been completed, further strengthening the structure.

🔹 4,500+ tonnes of reinforcement installed
🔹 15,000m³+ of concrete poured, including:

  • 6,500m³ for base slabs
  • 3,500m³ for perimeter walls

The site continues to evolve as key structural elements take shape. Further updates to follow!

More Info


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Leave a Reply

Your email address will not be published. Required fields are marked *

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading