5.3 T-Minus Guidelines for Possessions

The following table shows T-Minus guidelines by Possession Type. Requests received in advance of the minimum advertisment periods (refer section 3.3) may expedite the assessment and stakeholder engagement processes.

Possession Type: Configuration Closedown
T-Minus (Weeks) Actions
T-104 Initial Possession Assessment (Status: Pending)
T-103 Stakeholder Engagement Start
T-60 Stakeholder Engagement Concludes, Stakeholder Support Point
(Status: Approved / Declined)
T-10 Train Pathing Alteration Planning Start (Pending TRIMS Data
Availability)
T-4 Train Pathing Alteration Planning Complete
T-3 Draft TAA Published
T-2 Final TAA Published
T-0 Works Conducted

Possession Type: Major Closedown (> 60hrs in Duration)
T-Minus (Weeks) Actions
T-77 Initial Possession Assessment (Status: Pending)
T-70 Stakeholder Engagement Start
T-48 Stakeholder Engagement Concludes, Stakeholder Support Point
(Status: Approved / Declined)
T-10 Train Pathing Alteration Planning Start (Pending TRIMS Data
Availability)
T-4 Train Pathing Alteration Planning Complete
T-3 Draft TAA Published
T-2 Final TAA Published
T-0 Works Conducted

 

 

Possession Type: Total Possession (> 12hrs in Duration) & Total Possession (<=
12hrs in Duration) that impact on The Ghan & Indian Pacific services
T-Minus (Weeks) Actions
T-51 Initial Possession Assessment (Status: Pending)
T-48 Stakeholder Engagement Start
T-32 Stakeholder Engagement Concludes, Stakeholder Support Point
(Status: Supported / Not Supported)
T-10 Train Pathing Alteration Planning Start (Pending TRIMS Data
Availability)
T-4 Train Pathing Alteration Planning Complete, Possession Final
Approval Point (Status: Approved / Declined)
T-3 Draft TAA Published
T-2 Final TAA Published
T-0 Works Conducted

Possession Type: Total Possession (<= 12hrs in Duration) that impact on other
Passenger services
T-Minus (Weeks) Actions
T-23 Initial Possession Assessment (Status: Pending)
T-22 Stakeholder Engagement Start
T-12 Stakeholder Engagement Concludes, Stakeholder Support Point
(Status: Supported / Not Supported)
T-10 Train Pathing Alteration Planning Start (Pending TRIMS Data
Availability)
T-4 Train Pathing Alteration Planning Complete, Possession Final
Approval Point (Status: Approved / Declined)
T-3 Draft TAA Published
T-2 Final TAA Published
T-0 Works Conducted

Possession Type: Total Possession (<= 12hrs in Duration) that impact on Freight
services
T-Minus (Weeks) Actions
T-15 Initial Possession Assessment (Status: Pending)
T-14 Stakeholder Engagement Start
T-11 Stakeholder Engagement Concludes, Stakeholder Support Point
(Status: Supported / Not Supported)

T-10 Train Pathing Alteration Planning Start (Pending TRIMS Data
Availability)
T-4 Train Pathing Alteration Planning Complete, Possession Final
Approval Point (Status: Approved / Declined)
T-3 Draft TAA Published
T-2 Final TAA Published
T-0 Works Conducted

Possession Type: Possessions impacting on Grain Branch Lines
T-Minus (Weeks) Actions
T-7 Initial Possession Assessment (Status: Pending)
T-6 Stakeholder Engagement Start
T-4 Stakeholder Engagement Concludes, Stakeholder Support Point
(Status: Supported / Not Supported)
T-3 Train Pathing Alteration Planning Start
T-2 Train Pathing Alteration Planning Complete, Possession Final
Approval Point (Status: Approved / Declined), Final TAA Published
T-0 Works Conducted

Possession Type: Window Possession
T-Minus (Weeks) Actions
T-3 Possession Assessment (Approved / Declined)
T-2 TAA Published
T-0 Works Conducted
Table 3: T-Minus Guidelines

 


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO