hese apply to;
– Dual track sections of the network and include speed restriction on track adjacent to work sites where such restrictions may cause delays to services on adjacent lines, and
– Any temporary speed restriction (TSR) applicable prior to, during and after work is completed.
Parties requesting track possessions in areas where live line constraints potentially apply, must provide any proposed live line constraints to the NPM in the track possession application.
Any live line constraint will be considered in the track possession approval process, and if approved, be included in relevant track possession program, CTN or Safe Notice.