The CRN Possession Program will be updated and distributed to internal stakeholders, TAHE, rail operators, adjacent networks and other relevant parties. The possession program will be updated as required, where changes occur to works delivery or timing.
This possessions program will be published on or about the 20th of each month and distributed via email and uploaded to the John Holland CRN website www.jhrcrn.com.au .
Publication of Country Train Notices must be at least 7 days, and up to 42 days, prior to the commencement of a planned track possession.