Work train path requests for paths on the CRN must be sent to the Network Planning Manager at least 14 days prior to the commencement of a scheduled possession. Any amendment to a work train path on the CRN must be submitted to the CRN network programmer.
Any work train paths through the Sydney Trains or ARTC networks must submitted to those networks at least 28 days prior to the commencement of a scheduled possession.
Work train path requests, once approved, will be published in the form of CTNs.
The NPM will create a work train possession plan for each work train operating within a possession.