3.6. INFRASTRUCTURE RESTORATION

WARNING
Work in the Danger Zone must not commence until appropriate
Protection is in place.

Infrastructure restoration work in the Danger Zone arising from a CAN must be
undertaken only after the Protection Officer or Possession Protection Officer has
obtained the appropriate Work on Track Authority.