Perform the site-specific risk assessment.
Determine the level of risk that people, equipment or other objects will be less than
three (3) metres but greater than one (1) metre from Live OLE.
If that level of risk is not acceptable, then an OLE Permit to Work is normally required.
There is an exception to this.
Demonstrate that controls can be implemented so that the level of risk that anything
associated with the work, will be less than one (1) metre from Live OLE, is acceptable.
If that level of risk, with those controls in place, is acceptable, then a Vicinity Form must
be Issued, describing the controls.