7.2. IN DEPOTS

If Rail Traffic needs to be excluded from a work area within a depot, the PO must get
permission from the supervisor in charge of the depot.
The PO must make arrangements with the supervisor in charge of the depot to prevent Unauthorised entry of Rail Traffic into the work area.
The supervisor in charge of the depot must ensure Unauthorised entry of Rail Traffic into the work area is prevented.

NOTE
Follow the principles of the PTA Safeworking Rules and Procedures and apply Protection, closing roads by means of:
 clipping Points;
 stop signs; or
 Track Closed Warning Devices.