If the LPA involves more than one Worksite, the PPO uses the Worksite Permit Master
to:
maintain a record of Worksite Permits Issued; and
record Worksite handovers between POs.
The PPO must fill out a Worksite Permit Master that includes details about the:
works program Advertising the Authority;
intended start and finish times of the LPA;
LPA limits; and
number of Worksites included in the LPA.
For each Worksite, the PPO must record:
the PO’s name and contact details;
if Rail Traffic movements are associated with the Worksite;
the intended start and finish times for the work; and
the time and date when the Worksite Permit is Issued.
If the PO changes, the PPO must record the:
time of handover; and
incoming PO’s name and contact details.