6.5.2. MAINTAINING THE WORKSITE PERMIT MASTER

If the LPA involves more than one Worksite, the PPO uses the Worksite Permit Master
to:
 maintain a record of Worksite Permits Issued; and
 record Worksite handovers between POs.
The PPO must fill out a Worksite Permit Master that includes details about the:
 works program Advertising the Authority;
 intended start and finish times of the LPA;
 LPA limits; and
 number of Worksites included in the LPA.
For each Worksite, the PPO must record:
 the PO’s name and contact details;
 if Rail Traffic movements are associated with the Worksite;
 the intended start and finish times for the work; and
 the time and date when the Worksite Permit is Issued.
If the PO changes, the PPO must record the:
 time of handover; and
 incoming PO’s name and contact details.