When the work has been completed the PO must make sure:
that Rail Traffic and equipment is Clear of the Danger Zone;
that the Work Group has Cleared the Worksite;
that In-Field Protection and Point Clips have been removed;
the PPO is advised about operating restrictions that have been placed or removed;
and
the Worksite Permit is Fulfilled.
The PPO must:
use the Worksite Permit Master to record that the Worksite Permit has been
Fulfilled; and
ensure all Worksite Permits are Fulfilled before Fulfilling the LPA.