The PPO must:
make sure the PO protects their Worksites correctly; and
tell the POs if changes are required to Worksite Protection and make sure the
changes are carried out.
In-Field Protection for the Protection of Worksites within the LPA is a Rail
Clamped Worksite Limit Sign.
The PO must:
make sure that In-Field Protection is placed on each side of all Worksites, as shown
in the following examples:
FIGURE 6.2: Example of Protection arrangements for individual Worksites more than
400m apart.
FIGURE 6.3: Example of Protection arrangements for multiple Worksites more than
200m but less than 400m apart. Where both mains are affected by the works, they
must be protected appropriately
FIGURE 6.4: Example of protection arrangements for combined multiple Worksites less
than 200m apart. Where both mains are affected by the works, they must be protected
appropriately.