4.1. REQUEST FOR ABSOLUTE SIGNAL BLOCKING FROM WORKER OTHER THAN THE PROTECTION OFFICER

The Train Controller may apply ASB to allow station staff to access the Track or
Vehicles to directly cross the Track.
The Train Controller must:
 confirm the Location and the work to be done;
 make sure the Route is Clear between the Protecting Signals and the proposed
Worksite, and that any Rail Traffic that has passed the Worksite will not return;
 set the Protecting Signals at Stop and apply Blocking Facilities; and/or
 where the Signal has more than one Route available apply Blocking Facilities to
protect all entry points to the Worksite;
 advise the Worker of the arrangements and Authorise the work; and
 when told that the area is Clear, remove Blocking Facilities.


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO