5. OBTAINING APPROVAL FOR ABSOLUTE SIGNAL BLOCKING

The Train Controller and the PO must confirm and record on the Absolute Signal
Blocking Form:
 the kilometre Location of the Worksite;
 identify the Controlled Absolute Signals to be set and kept at STOP with Blocking
Facilities applied; and/or
 where the Signal has more than one Route available, identify the Route to the
Worksite and apply Blocking Facilities to protect all entry points;
 that Blocking Facilities have been applied or, where approved by the Train
Controller, the Crank Handle has been removed. The purpose of this precaution is
to prevent entry of Rail Traffic into the limits of the Worksite;
 the blocking Authority or identification number from the Train Control System;
 identification of the Points Secured;
 the PO’s name and contact details;
 the approving Train Controller’s name;
 the time of approval; and
 the date of approval.
When the ASB is approved the PO must put the required safety measures in place and
commence work.


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO