6. PROTECTION

WARNING
Work must not start in the Danger Zone until the required Protection is in
place.

The PO must arrange for:
 Controlled Absolute Signals to be set at Stop with Blocking Facilities applied; and/or
 where the Signal has more than one Route available apply Blocking Facilities to
protect all entry points to the Worksite; or
 the Crank Handle to be removed to set Controlled Absolute Signals at Stop.