Rail Traffic must be Fit For Purpose before access to and during Travel on the PTA
Network.
Rail Traffic must comply with the PTA’s gauge outline in accordance with PTA 8190-
400-001 Standard Gauge Mainline Code of Practice Track & Civil Infrastructure
and PTA 8190-400-002 Narrow Gauge Mainline Code of Practice Track & Civil
Infrastructure.
Rail Traffic Crew must not, without Authority, bypass, disconnect or turn off any device
provided for the safe operation of Rail Traffic.
Prior to entering the Network, Rail Traffic Crew must ensure that all necessary brake
tests have been performed and equipment is within specified limits.
Rail Traffic Integrity must be re-established whenever the Consist changes. Rail Traffic
Integrity must be documented and maintained.
Rail Traffic must be compatible with Civil Infrastructure standards.
Loading carried on Rail Traffic must be Secure and restrained safely throughout the
journey.