Any new scope of work submitted less than 12 weeks from the possession is considered late. Project Managers must seek formal approval by both their Deputy Executive Director (DED) and the DED, Asset Management Division in accordance with; Late Scope Request Process – AMD-ASD-GUI-002.
If the additional scope is approved by both DEDs the scope will be accepted in PACT
Any request for new scope of work after the Finalisation Meeting (which is held 4 weeks prior to the possession date) will not be accepted unless it is designated as “urgent2 work”. The request to carry out urgent work is assessed by the NAM. At this late stage, the impact to other scopes may be severe and may require the setting of priorities between scopes. Acceptance or rejection of “urgent work” is processed under the DED Approval process.
The impact, including Service Planning’s ability to amend and redistribute STNs will be conveyed to the respective DEDs in their consideration for approval of the scope inclusion.
The NAM and Program Coordinator also identifies and notifies relevant people on the impact the new scope has on combined worksites.
Refer: AS&DC SharePoint – Late Scope Request Guide (AMD-ASD-GUI-002)
Network Access Manual Volume 2
2 General Requirements
2.1 Master Schedule
2.2 Baseline Master Schedule
2.3 High-Level Scope and Resource Plan
2.4 Monthly Resource Confirmation meeting
2.5 Possession Planning Sequence
2.6 Program Coordination Unit (PCU)
2.7 Primavera (P6)
2.8 Possessions setup in PACT
2.9 Possession Constraints Register
2.10 Track Diagram
2.11 Possession bids in TRAK 2
2.12 Scope of work entered in PACT
2.13 Possession Start times
2.14 Late Scope Approval
2.15 Late/Change of Scope Submissions
2.16 Who Must Attend the Meetings
3 Works Coordination Meeting
3.1 Critical Projects for possession on time handback
3.2 Electrical Controls
3.3 Chronological Train List
3.4 Coordinated Worksites
3.5 Congested Worksites
3.6 Interface Issues
4 Finalisation Meeting
4.1 Final Chronological Train List
4.2 Coordinated Worksite Coordination Plans
4.3 Congested Worksites and Access Restrictions Plans
4.4 Records of Meetings
4.5 Possession Scope changes
5 Neighbour Notifications
5.1 Interface Issues
5.2 Late/Change of Scope Approval
6 Prepossession Meeting
6.1 Details Presented at Prepossession Meeting
6.2 Prepossession Meeting Notes Include Specific Forms
6.3 Worksite Incident Reporting
6.4 Work Train and Track Machine movements
6.5 Records of Meetings
7 Delivering the Possession
7.1 PPO Induction
7.2 Track Vehicle movements
7.3 Taking the Local Possession Authority
7.4 Possession Protection
7.5 Cascading the Prepossession Meeting Requirements
7.6 Work Commences
7.7 Possession Manager – Monitoring Critical Work
7.8 Possession Handback
7.9 Possession Reporting