The Baseline Master Schedule is developed by the Manager Asset Program Scheduling. This document describes the allocation of critical resources to scopes and also identifies resource shortfalls and scopes that are not deliverable due to resource constraints.
The High-Level Scope and Resource Plan is fine-tuned to become the Baseline Master Schedule. The Base Line Master Schedule is finalised 3 months before the delivery year begins.