2.5 Possession Planning Sequence

The Network Access Manager (NAM) sets up their regions Configuration and Closedown and Mid-Week templates in the Possession Access Coordination Tool (PACT) at least 20 weeks prior to the possession.
The template lists all relevant tracks and the protection constraints for each type of possession. Once the templates are established the NAM sets up possessions in PACT based on the Possession Program. Project Managers can then access PACT and register scopes of work to be delivered during specific possessions.
The NAM sets up their Districts possession bids in TRAK2 prior to the possession. TRAK2 entries require possession dates, summary of the reason for the possession, power isolation, track name and boundaries and special requirements.1
The Possession Support Officer (PSO) sets up their regions mid-week possessions in PACT based on the Mid-Week Possession Program at least 20 weeks prior to the possession.