2.7 Primavera (P6)

Capital Works being delivered by TfNSW Projects will be entered into P6 following the approval of scope of work via the Delivery Resource Assessment (DRA) process. Once DRA approval and required resources are assigned to deliver the work, the Program Coordinator will approve and assign the weekend and the Configuration Possession or Closedown to deliver the work. Once the works has been assigned by the Program Coordinator the scope is loaded into PACT for further planning.
Refer: AS&DC SharePoint – MS Delivery Resource Assessment Operational Procedure (AMD-ASD-SOP-002)