2.8 Possessions setup in PACT

Possessions are created in the PACT database by the NAM.
Closedown and Configuration Possessions are set up in PACT at least 20 weeks prior to the possession as per the Possession Program.
The Midweek possessions are set up in PACT at least 6 weeks prior to the possession as per the requirement of the Midweek Possession Calendar
Closedown, Configuration and Midweek Possession information is set up in PACT so that Project Managers from within Sydney Trains and from Transport Infrastructure and Services can register a scope of work to be delivered in a particular nominated possession.
PACT is used to plan and deliver possessions. The following information is recorded in PACT:
• Worksite scope details – actual start time, location, contacts
• Information relevant to the possession (PPO Diary – work train delays etc)
• Incidents
• Actual LPA staging start and handback times
• Protection placement and removal times
• Attachment of relevant documentation
• Production reporting
• Resource Scheduling
• Possession Scope Map
• Possession Management Plan Map


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO