The final version of the CTL is discussed and validated to confirm the track vehicle possession arrival and exit times and any overnight stabling arrangements.
Validation is required to confirm; work train configuration, train paths, TOC Waivers if applicable, track vehicle movements causing delays to critical scope of works and any unusual stabling arrangements.
Discussions will also validate and confirm arrangements and the timing for booking out infrastructure and the critical passage of track vehicles and the placement of protection prior to commencing work.
Network Access Manual Volume 2
2 General Requirements
2.1 Master Schedule
2.2 Baseline Master Schedule
2.3 High-Level Scope and Resource Plan
2.4 Monthly Resource Confirmation meeting
2.5 Possession Planning Sequence
2.6 Program Coordination Unit (PCU)
2.7 Primavera (P6)
2.8 Possessions setup in PACT
2.9 Possession Constraints Register
2.10 Track Diagram
2.11 Possession bids in TRAK 2
2.12 Scope of work entered in PACT
2.13 Possession Start times
2.14 Late Scope Approval
2.15 Late/Change of Scope Submissions
2.16 Who Must Attend the Meetings
3 Works Coordination Meeting
3.1 Critical Projects for possession on time handback
3.2 Electrical Controls
3.3 Chronological Train List
3.4 Coordinated Worksites
3.5 Congested Worksites
3.6 Interface Issues
4 Finalisation Meeting
4.1 Final Chronological Train List
4.2 Coordinated Worksite Coordination Plans
4.3 Congested Worksites and Access Restrictions Plans
4.4 Records of Meetings
4.5 Possession Scope changes
5 Neighbour Notifications
5.1 Interface Issues
5.2 Late/Change of Scope Approval
6 Prepossession Meeting
6.1 Details Presented at Prepossession Meeting
6.2 Prepossession Meeting Notes Include Specific Forms
6.3 Worksite Incident Reporting
6.4 Work Train and Track Machine movements
6.5 Records of Meetings
7 Delivering the Possession
7.1 PPO Induction
7.2 Track Vehicle movements
7.3 Taking the Local Possession Authority
7.4 Possession Protection
7.5 Cascading the Prepossession Meeting Requirements
7.6 Work Commences
7.7 Possession Manager – Monitoring Critical Work
7.8 Possession Handback
7.9 Possession Reporting