5.2 Late/Change of Scope Approval

No new scope or major changes to scope will be accepted at the Finalisation Meeting.
As a general rule, late scope will not be accepted within 12 weeks of the possession unless the work group’s DED and the DED Asset Management approve the scope for inclusion.
Any late scope that requires a new entry into TRAK 2 (Service Planning online tool to enter requests for all temporary timetable changes) which will subsequently change the STN or the Electrical Authority within the 12 weeks prior to the possession will not be considered, unless the changes can be accommodated by Service Planning, Electrical Engineering and Coordination Manager.
Late scope requested less than 14 days from the possession which requires an alteration in TRAK 2 (Power Outage and Possession Boundaries and Train Arrangements) will not be accepted.


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO