Representatives who attended the Prepossession Meeting must ensure that the information and documentation received at the meeting are cascaded in full to the Protection Officer (PO) on the first shift on their project. The first shift PO ensures all relevant details covered at the Prepossession Meeting are included in subsequent inductions to worksite staff.
Any following shift PO’s will also receive the information disseminated at the Prepossession Meeting during handover. This information is used to carry out any other site inductions.
Inductee’s name and signature are maintained.
POs provide the worksite protection component of the Pre-Work Briefing to all persons at the worksite.
Worksite Supervisors are responsible for providing Pre-Work Briefings which include the site-specific content for a worksite including reference to hazardous locations register in addition to any necessary information from the possession induction (possession notes) that may be required.
Network Access Manual Volume 2
2 General Requirements
2.1 Master Schedule
2.2 Baseline Master Schedule
2.3 High-Level Scope and Resource Plan
2.4 Monthly Resource Confirmation meeting
2.5 Possession Planning Sequence
2.6 Program Coordination Unit (PCU)
2.7 Primavera (P6)
2.8 Possessions setup in PACT
2.9 Possession Constraints Register
2.10 Track Diagram
2.11 Possession bids in TRAK 2
2.12 Scope of work entered in PACT
2.13 Possession Start times
2.14 Late Scope Approval
2.15 Late/Change of Scope Submissions
2.16 Who Must Attend the Meetings
3 Works Coordination Meeting
3.1 Critical Projects for possession on time handback
3.2 Electrical Controls
3.3 Chronological Train List
3.4 Coordinated Worksites
3.5 Congested Worksites
3.6 Interface Issues
4 Finalisation Meeting
4.1 Final Chronological Train List
4.2 Coordinated Worksite Coordination Plans
4.3 Congested Worksites and Access Restrictions Plans
4.4 Records of Meetings
4.5 Possession Scope changes
5 Neighbour Notifications
5.1 Interface Issues
5.2 Late/Change of Scope Approval
6 Prepossession Meeting
6.1 Details Presented at Prepossession Meeting
6.2 Prepossession Meeting Notes Include Specific Forms
6.3 Worksite Incident Reporting
6.4 Work Train and Track Machine movements
6.5 Records of Meetings
7 Delivering the Possession
7.1 PPO Induction
7.2 Track Vehicle movements
7.3 Taking the Local Possession Authority
7.4 Possession Protection
7.5 Cascading the Prepossession Meeting Requirements
7.6 Work Commences
7.7 Possession Manager – Monitoring Critical Work
7.8 Possession Handback
7.9 Possession Reporting