7.8 Possession Handback

Upon completion of work, prior to fulfilling the LPA the PPO must:

  • Confirm the location of work trains, track vehicles and Hi-Rails and workgroups have cleared the possession area and removed Worksite Protection
  • Confirm all possession protection including point clips, flags, RTS, lights and delineation lights have been removed
  • Confirm all points and signals are restored and tested before returning the track for service.
    Confirm power has been restored
  • Advise the Network Control Officer of any speed restrictions or other restriction that may affect track usage
  • Advise the Network Control Officer of staged handback or addition track work authority if additional protection will be required following the LPA to complete any work
  • Ensure that all work groups have signed and forwarded a copy of the following to the PMC:
    o Infrastructure Handover and Certification Form and restoration checklist – forms which have Booked Out infrastructure or Residual Risk identified on the form (Refer Possession Notice 10) are to be collated and sent to the ICON Duty Manager
    o Infrastructure Booking Authority (where applicable)
    o Report (for Safety, SafeWorking, Damage, Environmental, or Reliability incident).

Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO