8 Mid – Week Possessions

All Mid-Week possessions are created in PACT (based on the Mid- Week possession program), and the PACT system used to manage the possessions. For the Central District, the Possession Support Officers (PSO) will enter their regular nightly scopes into PACT, and only additional (non-regular) work groups will enter their own scopes.
Mid-Week possessions are set up at least 2 weeks prior to possession where possible. Other district PSO’s are to hold regular planning meetings with NMD and MW staff approximately 20 weeks prior to possession and scopes are to be entered into PACT by the relevant workgroup. In the lead up to the possession, minimum 2 weeks prior, the PSO is to prepare the possession documentation (briefing notes, constraints registers) and resolve any potential clashes of worksites.
On a nightly basis, all PO’s are to report to the PPO’s office for a meeting to confirm work locations and possession briefing.

 

 

 


 

Network Access Manual Volume 2

1 Background

2 General Requirements
2.1 Master Schedule
2.2 Baseline Master Schedule
2.3 High-Level Scope and Resource Plan
2.4 Monthly Resource Confirmation meeting
2.5 Possession Planning Sequence
2.6 Program Coordination Unit (PCU)
2.7 Primavera (P6)
2.8 Possessions setup in PACT
2.9 Possession Constraints Register
2.10 Track Diagram
2.11 Possession bids in TRAK 2
2.12 Scope of work entered in PACT
2.13 Possession Start times
2.14 Late Scope Approval
2.15 Late/Change of Scope Submissions
2.16 Who Must Attend the Meetings

3 Works Coordination Meeting
3.1 Critical Projects for possession on time handback
3.2 Electrical Controls
3.3 Chronological Train List
3.4 Coordinated Worksites
3.5 Congested Worksites
3.6 Interface Issues

4 Finalisation Meeting
4.1 Final Chronological Train List
4.2 Coordinated Worksite Coordination Plans
4.3 Congested Worksites and Access Restrictions Plans
4.4 Records of Meetings
4.5 Possession Scope changes

5 Neighbour Notifications
5.1 Interface Issues
5.2 Late/Change of Scope Approval

6 Prepossession Meeting
6.1 Details Presented at Prepossession Meeting
6.2 Prepossession Meeting Notes Include Specific Forms
6.3 Worksite Incident Reporting
6.4 Work Train and Track Machine movements
6.5 Records of Meetings

7 Delivering the Possession
7.1 PPO Induction
7.2 Track Vehicle movements
7.3 Taking the Local Possession Authority
7.4 Possession Protection
7.5 Cascading the Prepossession Meeting Requirements
7.6 Work Commences
7.7 Possession Manager – Monitoring Critical Work
7.8 Possession Handback
7.9 Possession Reporting

8 Mid – Week Possessions

Version Control Table

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO