Sydney, 15 Metres Below Westmead

Current Progress

The excavation works at Westmead have reached a major milestone — 15 metres underground.

  • Roadheaders and rock hammers have completed excavation of the massive crossover cavern.

  • The cavern features a cathedral-like design, carved deep into the ground.

Purpose of the Crossover Cavern

  • This structure allows trains to switch tracks after departing Westmead.

  • It provides greater operational flexibility for services heading back toward the Sydney CBD.

Next Steps

With excavation complete, the focus now shifts to:

  • Waterproofing

  • Steel fixing

  • Formwork installation

  • Concreting works

 

[More Info]

Tagged:

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading