Current Progress
The excavation works at Westmead have reached a major milestone — 15 metres underground.
-
Roadheaders and rock hammers have completed excavation of the massive crossover cavern.
-
The cavern features a cathedral-like design, carved deep into the ground.
Purpose of the Crossover Cavern
-
This structure allows trains to switch tracks after departing Westmead.
-
It provides greater operational flexibility for services heading back toward the Sydney CBD.
Next Steps
With excavation complete, the focus now shifts to:
-
Waterproofing
-
Steel fixing
-
Formwork installation
-
Concreting works