New Intercity Fleet (NIF) Platform Extension Projects Analysis

Platform extension projects for the New Intercity Fleet involve complex staging and interface management to accommodate longer trains while maintaining operational stations. Production rates vary based on platform configuration, existing infrastructure, and construction methodology. Modern techniques including prefabricated elements and modular construction have improved delivery timeframes, with some projects achieving extension rates of up to 40m per week under optimal conditions.

Key Statistics:

  • Average extension length: 60-80m
  • Typical platform width: 3.5-4.5m
  • Production rate: 20-30m/week
  • Concrete pour volume: 30-40m³/day
  • Typical project duration: 4-6 months
  • Best practice completion: 3 months
  • Average cost: $3-5M per platform
  • Typical possession utilization: 85%

AUSTRALIA REGION (NSW NIF Projects)

Station Scope Length (m) Elements Duration (months) Start-End Production Rate (m/week) Contractor Cost ($M) Source
Wyong Platform 1&2 75 PE,CS,OHW 5 Mar20-Aug20 25-30 John Holland 4.2 TfNSW
Gosford Platform 3&4 80 PE,CS,OHW 6 Jun20-Dec20 20-25 Downer 4.8 NIF Data
Woy Woy Platform 1&2 65 PE,CS,OHW 4 Sep20-Jan21 28-32 Haslin 3.8 TAHE
Hornsby Platform 4&5 70 PE,CS,OHW 5 Apr21-Sep21 22-28 Built 4.5 RAP Reports
Newcastle Platform 1 60 PE,CS,OHW 4 Jul21-Nov21 25-30 John Holland 3.6 TfNSW Data

Key:
PE = Platform Extension
CS = Canopy/Shelter
OHW = Overhead Wiring Modifications

Production Rate Analysis by Element:

Platform Construction:

  1. Foundation Works:
  • Piling: 4-6 piles/day
  • Footings: 15-20m/week
  • Retaining walls: 10-12m/week
  1. Platform Structure:
  • Precast panels: 8-10 units/day
  • In-situ concrete: 20-25m³/day
  • Surface finishing: 100m²/week
  1. Services/Utilities:
  • Drainage: 15-20m/day
  • Electrical: 25-30m/day
  • Communications: 20-25m/day

Would you like me to continue with more stations and detailed analysis?

Note 1: Production rates are indicative only.

Note 2: Rates vary based on:

  • Existing platform condition
  • Access constraints
  • Service relocations
  • Possession availability
  • Weather impacts
  • Interface requirements

Note 3: Duration calculation formula:
D = (BL × CF × IF) + PC, where:

  • D = Total duration
  • BL = Base length duration
  • CF = Complexity factor (1.0-1.5)
  • IF = Interface factor (1.0-1.3)
  • PC = Possession constant

Influencing Factors:

  • Station operations
  • Heritage requirements
  • Utility interfaces
  • Weather impacts
  • Material lead times
  • Approval processes
  • Community impacts
  • Rail possession availability

 


Other production rates – Indicative only

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock