Post-blockade rail operations resume with OLE foundation installation, track removal for bridge reconstruction, and tunnel works...
Successful transport and installation of 26-tonne footbridge during 26-hour possession, navigating 14 point sets with early handback...
Successful delivery of points 9452B half set during Week 12 of CVL project, achieving zero incidents while coordinating multiple works...
First passenger platform installation at Old Oak Common marks transition from construction to operational infrastructure for HS2 super-hub...
Successful high-speed rail switch renewal operation at Solers achieves speed enhancement from 120 to 160 km/h through coordinated implementation...
Significant architectural milestones have been achieved at two key Cross River Rail stations, with the installation of skylights at Woollongabba Station and the completion of the canopy structure at B...
Strategic points renewal at Motherwell Weighs demonstrates advanced pre-fabrication implementation and complex geometry management...
Complex network of tunnels, viaducts, and bridges takes shape for HS2 Birmingham approaches, integrating high-speed rail into urban fabric...
Alstom initiates CEO succession planning as Henri Poupart-Lafarge announces intention not to seek fourth term ending March 2027...
Ormeau rail facility development progresses with 1,755 tonnes of track delivery and 3,000 ground improvement columns installation...
Historic Osormort Viaduct receives innovative cable-stay system upgrade, enhancing structural integrity and maintenance capabilities...
Specialist ballast operation successfully installs 4,220 tonnes over 11km between Yass and Binalong, completing ahead of schedule...
Completion of complex Hunter Street station excavation marks major milestone in Sydney Metro West development, preparing for tower construction...
Australia, Sydney – Brookvale Bus Depot Electrification: Zero-Emission Infrastructure Implementation
Brookvale Bus Depot nears completion of electric charging infrastructure, advancing zero-emission public transport implementation...
Australia, Western Australia – Esperance Line Culvert Replacement Project: Multi-Site Implementation
A coordinated infrastructure upgrade operation on the Arc Network’s Esperance Line involves the unloading of materials for four culvert replacements, scheduled for completion during the June shu...
Critical signaling upgrade completed on NSW Interstate Network, enhancing security and reliability through modern coded track technology...
Complex rail-based delivery of 35-metre switches demonstrates innovative solution to access constraints at Stoke Junction...
CRS Alliance Crewe successfully executes S&C renewal at Dallam Junction within 76.59-hour possession window, maintaining project schedule...
Advanced continuous surface mining technology accelerates Mount Street underpass completion, demonstrating innovative infrastructure development...
Project Overview A significant urban mobility improvement project is underway at Calder Park Drive, featuring the installation of an innovative switchback-style shared use path on the eastern side of ...
Historic roundabout design facilitates SMART rail expansion, demonstrating successful infrastructure planning and transit system integration...
Emergency services complete comprehensive familiarization program for new metro stations, enhancing operational readiness and response capabilities...
Sydney Metro project update: First tracks laid at Luddenham....
TBM Ruby advances Sydney Metro West development with precision segment installation, showcasing advanced tunnelling technology...
Precision engineering operation successfully installs massive steel beams at Marrickville bridge, advancing Sydney Metro's T3 line conversion...
Pioneering deployment of Australia's exclusive SENNEBOGEN 613 enhances railway infrastructure maintenance capabilities in Bulli's coastal environment...
Auckland's Central Interceptor achieves complete tunnelling milestone, marking engineering excellence in wastewater infrastructure development...
Project Overview The collaboration between Davis Crane Services and South Point Contractors demonstrates effective coordination in heavy lifting operations. The project involves beam installation as p...
Project Overview The construction of the “New Riol Access Road” began near the Eisack underpass in Franzensfeste, marking a significant infrastructure development initiative. Key Component...
Project Highlights ✔ Dallas to Houston in under 90 minutes ✔ 200+ mph operating speeds ✔ Departures every 30 minutes during peak times ✔ Zero fatalities in over 50 years of N700 train operations ✔ All...
Scope of Work Reballasting Resleepering Re-railing Equipment Used 2 × DX270 excavators for scraping 1 × DX140 for sleeper handling AR17 Personnel Carrier (due to 1-mile distance from access point) Pro...
Government officials conducted an on-site inspection of the western extension of Line 6 today. The delegation included: Juan Carlos Muñoz, Minister of Transport and Telecommunications Guillermo Muñoz,...
Over the Easter long weekend, Shotcrete Australia successfully completed high-risk geotechnical stabilisation works at two critical rail cuttings on Sydney‘s South Coast Line, delivering an ambi...
Laing O’Rourke, as part of the ActivUs Alliance, has been appointed to deliver the design and pre-construction works for Queensland’s landmark Logan and Gold Coast Faster Rail project – a critical upg...
Laing O’Rourke’s Rail Operations team in Victoria has successfully delivered complex structural repairs at Geelong Tunnel, showcasing exceptional project execution under challenging conditions. Projec...
Transport Infrastructure Ireland (TII) has announced the Emerging Preferred Route for Luas Cork and is inviting the public to share feedback on the proposed plan. The consultation will run for eight w...
This Easter, the VolkerRail POMs team delivered outstanding results across multiple sites, supporting VolkerRail and Network Rail on the #SRE contract—all while maintaining our commitment to safety, p...
Eglinton Crosstown West Extension (ECWE) Project The multicultural Greater Toronto Area’s transit system is undergoing significant expansion. One of the key projects currently in progress is the Eglin...
The BrennerBaseTunnel will stretch 55 km between Fortezza (Italy) and Innsbruck (Austria), connecting underground to the existing bypass railway (also tunneled), reaching a total length of 64 km. Once...
Overview Swietelsky Rail Australia (SRA) successfully completed a major closedown in the Hunter Valley earlier this month. Key Achievements SRA’s 08-275 Unimat consist was deployed near Bengalla...
Project Launch: Sydney Metro – Western Sydney Airport Rhomberg Sersa Australia (RSA) has officially begun work on the Sydney Metro – Western Sydney Airport project, a landmark infrastructure developme...
Project Progress Update: Tunnelling and Viaduct Construction Highlights Key Achievements This Week 1. Tunnelling Machine “Sushila” Successfully Extracted The massive tunnelling machine Sus...
Progress Update Crews poured 280,000 litres of concrete to form the foundations of the new Hopkins Road bridge. Two piling rings dug 48 piles. Road bridge embankments are under construction, with 72,0...
Weekend Rail Upgrade in Full Swing Another Saturday afternoon, another successful upgrade on the Transpennine Route Upgrade (TRU)! A new Switches and Crossings (S+C) installation was completed between...
Lighting Up the Future of Transport 💡 The future is looking bright at Woolloongabba Station as it edges closer to completion. A recent lighting test on the platform has brought the space to life With ...
Works Completed The piling works at Watsons Road in Diggers Rest have now been completed. A 65-tonne piling rig was used to dig the foundation piles. These piles will support the new road bridge over ...
Turnouts and Track Upgrades Supporting Regional Growth Teams from Arc Infrastructure‘s Major Projects, Mobile Maintenance Team (MMT), and Goldfields-Esperance region joined forces with other int...
March Super Possession Success for ARTC It was a huge weekend for the Rail Ops NSW team, who successfully delivered major works across the Main South lines for ARTC during the March Super Possession. ...
Presentation Highlights from Sean McAllister The extensive Moondyne west end turnout replacement project was recently featured in a presentation by Sean McAllister, Project Lead – Track, at the #RailT...
Over the weekend, teams were deployed across various networks delivering multiple work scopes including: Berry Track Recon Track support services for Sydney Trains Rail Rake operations for ARTC Planni...
Testing Update Summer might be over, but sand is still making an appearance—this time in the form of 45 tonnes of sandbags loaded into a test train as part of the latest dynamic testing phase for Auck...
Event Summary Last weekend, the Sydney Metro West – Eastern Tunnelling Package team welcomed local residents to the Pyrmont West site for a special behind-the-scenes experience. Community Engagement H...
A Major Milestone for Sydney Metro – Western Sydney Airport Line The first tracks have been laid for the Sydney Metro – Western Sydney Airport line, marking a significant achievement in the 23-kilomet...
Sydney Metro West – Hunter Street Station Overview A glimpse into the Sydney Metro West project. Hunter Street Station is a key development in the Sydney CBD. Viewable from George Street....
Project Overview Successfully delivered track reconditioning works for ARTC Location: Adjacent to Heritage Listed Cootamundra West Railway Station Scope: 180m section of track reconditioning Timing: S...
Strong Start to the Year by Gamuda Laing O’Rourke Consortium The Gamuda Australia and Laing O’Rourke Consortium has launched into the year with impressive progress at the future Westmead m...
Progress is well underway as we tunnel beneath Sydney Harbour, connecting The Bays Station in Rozelle to the Sydney CBD. Pyrmont Station Cavern Works Three roadheaders are actively excavating the Pyr...
WEBUILD JV SIGNS AU$1.7 BLN (€1 BLN) CONTRACT ON MASSIVE RAIL PROJECT IN MELBOURNE, AUSTRALIA SUBURBAN RAIL LOOP TO EXPAND CITY’S SUSTAINABLE MOBILITY NETWORK JV partners, led by Webuild, will design,...
A monumental day at the Keighley & Worth Valley Railway as volunteers & contractors landed the new 50-ton bridge across the Bridgehouse Beck, the biggest civil engineering project the railway ...
This map shows a summary of planned improvement work taking place across GWR (Great Western Railway) network. Full details of this work can be found on the next pages. You can check your journey detai...
This map shows a summary of planned improvement work taking place across GWR (Great Western Railway) network. Full details of this work can be found on the next pages. You can check your journey detai...
August recap. Its not all underground stations on Cross River Rail. Re-building eight stations north and south of the underground line. More info So here’s some progress shots Possession PlanningPoss...
Australia, Sydney, North Strathfield Station site, Tunnel boring machines (TBMs) Daphne and Beatrice
Tunnel boring machines (TBMs) Daphne and Beatrice are nearing the end of their journey! After breaking through at North Strathfield Station site, they now have less than two kilometres of tunnel to bu...
Moving into the shed extension for the embedded, concrete wall and steel column rail construction systems starting off with the steel columns on road 1&2. Interesting and fiddly this one but it’s ...
The double TBM breakthrough marks a milestone achievement for the Sydney Metro West – Western Tunnelling Package and the Gamuda Australia and Laing O’Rourke. TBM Betty and Dorothy have completed...
The Stockinbingal to Parkes section of Inland Rail is now six months ahead of schedule, thanks to Martinus’ strategic foresight as the head contractor and our close partnership with Inland Rail. By im...
Pune & Pimpri-Chinchwad is the next largest urban conglomerate to Mumbai Metropolitan Region in Maharashtra. These cities are considered to be educational hubs due to the establishment of large nu...
The T3 Bankstown Line will be closed between Sydenham to Bankstown from Saturday 24 August to Sunday 25 August 2024 for a planned rail possession. Sydney Metro work will take place in the rail corrido...
A successful trip to the Hunter Valley for the ARTC shutdown over the weekend. 3 days worth of semi tricky scope completed in under 2/3 of the time allocated, across 3 different sites (which required ...
Matic are absolutely thrilled to have played a key role in one of Sydney‘s most complex infrastructure projects! They have successfully completed the installation of two bridge girders that will...
Final commissioning of More Trains More Services works at Waterfall, in a special nine day possession. Over the last four years, there has been extensive remodelling of track, OHW and station platform...
Possession PlanningPossession Planning is dedicated to providing news and insights for rail and road possession planning and delivery. Our mission is to serve as the premier information source for ind...
ARTC, Safe Notice 2-5566 ARTC & Sydney Trains LPA limit protection arrangements WE02 Config 10B Possession PlanningPossession Planning is dedicated to providing news and insights for rail and road...
ARTC-Interstate-Possesssions-Calendar-May-2024-Update Possession Planning – Current Possession Calendars Latest Possession Calendars Australia ARTC https://possessionplanning.com/p...
Cross River Rail is a 10.2km rail line from Dutton Park to Bowen Hills, which includes 5.9 kilometres of twin tunnels under the Brisbane River and Brisbane CBD. The project includes construction of fo...
Philadelphia's Penn Coach Yard undergoes major transformation with new Heavy Maintenance Facility, advancing Northeast Corridor rail operations...
ARTC-Interstate-Possession-Calendar-November-2023-Update Our Partners FR2 Infrastructure – Constructability advise and project and planning controls Staging Diagrams – Stagi...
Latest ARTC Possession Calendars ARTC, HUNTER VALLEY, 2023, ANNUAL POSSESSION PROGRAMME, Version 5 Possession PlanningPossession Planning is dedicated to providing news and insights for rail an...
A New Road over rail bridge is now in use at Burrucoppin on the East / West Line of the Arc network Source Possession PlanningPossession Planning is dedicated to providing news and insights for...
Network closures calendar Month – Years Line Start Location End Location Service Disruption Last passenger service Track Clear Track Hand Back First passenger service 2023 Dec-23 L2L3 Circular ...
Innovative Wellington-made technology to protect the rail line while building the Ngā Ūranga ki Pito-One (Ngauranga to Petone) section of Te Ara Tupua, the project to improve State Highway 2’s r...
Latest Possession Calendars Track possession applications are subject to minimum application periods and various other factors before approval is given to conduct the works. The Interstate Possessions...
Latest Possession Calendars 220725-221106 future-trackwork-calendar Possession PlanningPossession Planning is dedicated to providing news and insights for rail and road possession planning and ...
Description: Major Closedown and Weekend Possession Programme Effective Date: Mon 14 Feb 2022 Version: Version 5.0 Source: Link Possession PlanningPossession Planning is dedicated to providing news an...
Source: https://www.artc.com.au/uploads/OPE-PR-045-Interstate-Possession-Planning-and-Approval-V2.0.pdf Possession PlanningPossession Planning is dedicated to providing news and insights for rail and ...