Significant progress achieved in Sydney Trains’ MVP Resignalling project through collaborative efforts between project teams and delivery partners, completing Stages 2 & 3 and preparing for final commissioning.

Annual Achievements

Infrastructure Type Quantity Implementation
Turnout Crossovers 2 units Complete installation
New Track 450m siding With catchpoint
Drainage 500m+ New track system
ULXs 23 units Full installation
Signals 17 units Installed & erected
Signal Buildings 4 units Ready for fitout

Power Infrastructure

Component Status Delivery
Substation Negative Upgraded Morisset facility
Positive Feeding New structure Ready for changeover
Transformers 2 padmounts Commissioned
CSR Routes 5km+ New installation
OHW Structures Complete New track integration

 


More Info


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

By Possession Planning

Possession Planning is dedicated to providing news and insights for rail and road possession planning and delivery. Our mission is to serve as the premier information source for industry professionals managing critical infrastructure access, maintenance windows, and construction scheduling. Our Partners: FR2 Infrastructure | We Simplify Complexity | Construction Methodology | S | Energy Planning | Staging Diagrams . |

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading