Significant progress achieved in Sydney Trains’ MVP Resignalling project through collaborative efforts between project teams and delivery partners, completing Stages 2 & 3 and preparing for final commissioning.
Annual Achievements
| Infrastructure Type | Quantity | Implementation |
|---|---|---|
| Turnout Crossovers | 2 units | Complete installation |
| New Track | 450m siding | With catchpoint |
| Drainage | 500m+ | New track system |
| ULXs | 23 units | Full installation |
| Signals | 17 units | Installed & erected |
| Signal Buildings | 4 units | Ready for fitout |
Power Infrastructure
| Component | Status | Delivery |
|---|---|---|
| Substation Negative | Upgraded | Morisset facility |
| Positive Feeding | New structure | Ready for changeover |
| Transformers | 2 padmounts | Commissioned |
| CSR Routes | 5km+ | New installation |
| OHW Structures | Complete | New track integration |
Possession Planning is dedicated to providing news and insights for rail and road possession planning and delivery. Our mission is to serve as the premier information source for industry professionals managing critical infrastructure access, maintenance windows, and construction scheduling.
Our Partners: FR2 Infrastructure | We Simplify Complexity | Construction Methodology | S | Energy Planning | Staging Diagrams . |
Discover more from Possession Planning
Subscribe to get the latest posts sent to your email.