6.5.4. FULFILLING A WORKSITE PERMIT

When the work has been completed the PO must make sure:
 that Rail Traffic and equipment is Clear of the Danger Zone;
 that the Work Group has Cleared the Worksite;
 that In-Field Protection and Point Clips have been removed;
 the PPO is advised about operating restrictions that have been placed or removed;
and
 the Worksite Permit is Fulfilled.
The PPO must:
 use the Worksite Permit Master to record that the Worksite Permit has been
Fulfilled; and
 ensure all Worksite Permits are Fulfilled before Fulfilling the LPA.