HDD operations require precise coordination of drilling operations, fluid management, and pipe installation. Production rates vary based on ground conditions, pipe diameter, and drilling length. Modern guidance systems and drilling technologies have improved installation accuracy and efficiency.
Key Statistics:
- Average production: 150-200m/day
- Typical depths: 5-25m
- Diameters: 100-1200mm
- Best practice: 250m/day
- Pullback force: 10-100t
- Drilling fluid: 200-1000L/min
- Accuracy: ±50mm
- Design life: 50+ years
INTERNATIONAL EXAMPLES
| Country | Location | Length (m) | Diameter (mm) | Rate (m/day) | Ground Type | Contractor | Cost ($K/m) | Source |
|---|---|---|---|---|---|---|---|---|
| Australia | Sydney | 450 | 900 | 150-180 | Sandstone | UEA | 3.2 | Sydney Water |
| UK | London | 380 | 600 | 180-200 | London Clay | Murphy | 2.8 | Thames Water |
| Germany | Hamburg | 520 | 800 | 160-190 | Mixed | Herrenknecht | 3.5 | DB |
| USA | Houston | 680 | 1000 | 140-170 | Clay/Sand | Laney | 3.8 | City Houston |
| Singapore | Jurong | 420 | 750 | 170-200 | Marine Clay | McConnell Dowell | 3.0 | PUB |
Installation Phase Analysis:
PILOT BORE:
- Production Rates:
- Soft ground: 200-250m/day
- Mixed ground: 150-180m/day
- Rock: 80-100m/day
- Setup time: 4-6 hours
- Requirements:
- Tracking system
- Fluid management
- Survey control
- Ground monitoring
REAMING OPERATIONS:
- Production Rates:
- First pass: 150-180m/day
- Final pass: 100-120m/day
- Multiple passes needed >600mm
- Back reaming: 80-100m/day
Note 1: Production rates are indicative only.
Note 2: Rates vary based on:
- Ground conditions
- Pipe diameter
- Length of drill
- Access conditions
- Fluid management
- Equipment capacity
Note 3: Installation calculation formula:
P = (BL × DF × GF × AF) – DC, where:
- BL = Base length
- DF = Diameter factor (0.7-1.2)
- GF = Ground factor (0.6-1.0)
- AF = Access factor (0.8-1.1)
- DC = Delay constant
Key Considerations:
- Fluid management
- Ground stability
- Surface monitoring
- Environmental controls
- Utility detection
- Quality assurance
- Emergency response
- Documentation requirements
Other production rates – Indicative only
- RAIL INDUSTRY PRODUCTION RATES COMPREHENSIVE TABLE
-
- Ballast Cleaning Operations Analysis
- Canopy Installation Analysis for Aerial Concourses
- Cut and Fill Production Rates in Railway Station Construction
- CSR (Cable Service Routes) Installation Analysis
- Demolition Works Analysis for Railway Infrastructure
- Electrical Overlaps (OHW) 33kV Installation Analysis
- Elevated Service Access Platforms (ESAPs) for Stabling Yards Analysis
- Escalator Installation Analysis for Rail Stations
- Fence Installation Between Tracks Analysis (Live Corridor vs Possession Works)
- HDD Under Rail Tracks – 48-Hour Possession Analysis
- High-Speed Rail Construction Analysis
- Horizontal Directional Drilling (HDD)
- Lght Rail Construction Production Rates: Global Analysis
- Lift Replacement Projects Analysis
- Mechanical Gap Fillers Installation Analysis
- New Aerial Concourse Installation Analysis for Train Stations
- New Intercity Fleet (NIF) Platform Extension Projects Analysis
- Overhead Wire (OHW) Structure Installation Analysis
- Platform Extension Projects: Global Analysis
- Platform Marker Repainting Analysis
- Railway Sleeper Replacement Analysis
- Roadheader Production Rates in Underground Station Construction: Global Performance Analysis
- Screen Indicator Installation Analysis for Rail Stations
- Segregation Fence Installation Analysis Between Tracks
- Slab Track Construction in Railway Stations: Global Production Analysis
- Sound Barrier Installation Analysis Along Rail Corridors
- Stabling Yard Construction and Production Analysis
- Track Replacement in Railway Stations: Production Analysis
- Transport Access Program (TAP) Production Rates and Delivery Analysis
- Tunnel Boring Machine (TBM) Production Analysis and Performance Metrics
- Tunnel Membrane/Waterproofing Installation Analysis
- Under Line Crossing (ULX) Installation Analysis
- Underpass Access Construction Analysis for Train Stations
- Utilities Relocation in Railway Environments Analysis
- Water-Filled Traffic Barriers Installation Analysis