Lift replacement in railway stations requires precise coordination of demolition, structural modifications, and new installation while maintaining station operations. Production rates vary based on lift configuration, station complexity, and access constraints. Modern installation techniques and pre-manufactured lift systems have improved delivery timeframes, with some projects achieving complete replacements in 12-14 weeks under optimal conditions.
Key Statistics:
- Average replacement duration: 16-20 weeks
- Demolition phase: 2-3 weeks
- Installation phase: 8-10 weeks
- Testing period: 2-3 weeks
- Typical lift height: 4-12m
- Best practice completion: 12 weeks
- Average cost: $800K-1.2M per lift
- Operational reliability target: 99.5%
AUSTRALIA REGION
| Location | Station | Scope | Height (m) | Type | Duration (weeks) | Start-End | Production Rate | Contractor | Cost ($M) | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Sydney | Central | 2 Lifts | 8.5 | Schindler | 18 | Mar21-Jul21 | 9 weeks/lift | Liftronic | 2.1 | TfNSW |
| Melbourne | Flinders | 3 Lifts | 10.2 | KONE | 24 | Jun20-Dec20 | 8 weeks/lift | Otis | 3.4 | MTM |
| Brisbane | Roma St | 2 Lifts | 6.8 | Otis | 16 | Sep21-Jan22 | 8 weeks/lift | Schindler | 1.8 | QR |
| Sydney | Strathfield | 2 Lifts | 7.5 | ThyssenKrupp | 20 | Apr21-Sep21 | 10 weeks/lift | KONE | 2.2 | Sydney Trains |
| Perth | Perth Stn | 2 Lifts | 9.0 | KONE | 18 | Jul21-Nov21 | 9 weeks/lift | Liftronic | 2.0 | PTA |
NTERNATIONAL LIFT REPLACEMENT EXAMPLES
UK REGION
| Location | Station | Scope | Height (m) | Type | Duration (weeks) | Start-End | Production Rate | Contractor | Cost ($M) | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| London | Victoria | 4 Lifts | 12.5 | Otis Gen3 | 28 | Mar21-Sep21 | 7 weeks/lift | Otis UK | 3.8 | Network Rail |
| Manchester | Piccadilly | 3 Lifts | 9.8 | KONE MonoSpace | 21 | Jun20-Nov20 | 7 weeks/lift | KONE | 2.9 | TfGM |
| Birmingham | New Street | 5 Lifts | 15.2 | Schindler 5500 | 32 | Apr21-Dec21 | 6.5 weeks/lift | Schindler | 4.5 | Network Rail |
EUROPEAN REGION
| Location | Station | Scope | Height (m) | Type | Duration (weeks) | Start-End | Production Rate | Contractor | Cost ($M) | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Paris | Gare du Nord | 6 Lifts | 14.0 | Thyssen Evolution | 36 | May21-Jan22 | 6 weeks/lift | ThyssenKrupp | 5.2 | SNCF |
| Berlin | Hauptbahnhof | 4 Lifts | 16.5 | KONE TranSys | 24 | Jul20-Jan21 | 6 weeks/lift | KONE | 3.9 | DB |
| Amsterdam | Centraal | 3 Lifts | 11.2 | Schindler 7000 | 18 | Sep21-Jan22 | 6 weeks/lift | Schindler | 2.8 | NS |
ASIAN REGION
| Location | Station | Scope | Height (m) | Type | Duration (weeks) | Start-End | Production Rate | Contractor | Cost ($M) | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Hong Kong | Central | 5 Lifts | 18.5 | Mitsubishi NexWay | 30 | Feb21-Sep21 | 6 weeks/lift | Mitsubishi | 4.8 | MTR |
| Singapore | Orchard | 4 Lifts | 13.2 | Fujitec GLVF | 24 | Aug20-Feb21 | 6 weeks/lift | Fujitec | 3.6 | LTA |
| Tokyo | Shinjuku | 6 Lifts | 15.8 | Hitachi GP | 32 | Mar21-Nov21 | 5.5 weeks/lift | Hitachi | 5.5 | JR East |
Regional Performance Analysis:
Europe:
- Average duration: 6-7 weeks/lift
- Higher automation levels
- Stricter safety standards
- Better access management
Asia:
- Average duration: 5.5-6.5 weeks/lift
- Advanced technology integration
- 24/7 work patterns
- Higher passenger volumes
UK:
- Average duration: 6.5-7.5 weeks/lift
- Heritage considerations
- Complex stakeholder management
- Strict possession requirements
Technology Variations:
Modern Systems:
- Machine Room-Less:
- Installation: 5-6 weeks
- Testing: 1-2 weeks
- Commissioning: 1 week
- Traditional Systems:
- Installation: 7-8 weeks
- Testing: 2 weeks
- Commissioning: 1-2 weeks
Smart Features:
- Destination control
- Predictive maintenance
- Energy regeneration
- Remote monitoring
Regional Compliance Requirements:
European Union:
- EN 81-20/50 standards
- Energy efficiency requirements
- Accessibility compliance
- Safety documentation
Asia Pacific:
- Local building codes
- Seismic requirements
- High-rise specifications
- Humidity protection
UK Standards:
- BS EN 81 series
- Network Rail standards
- DDA requirements
- Fire regulations
Cost Analysis by Region:
Europe:
- Base cost: €600K-800K/lift
- Labor: 35-40%
- Materials: 45-50%
- Overheads: 15-20%
Asia:
- Base cost: $700K-900K/lift
- Labor: 30-35%
- Materials: 50-55%
- Overheads: 15%
UK:
- Base cost: ÂŁ500K-700K/lift
- Labor: 40-45%
- Materials: 40-45%
- Overheads: 15-20%
Note: All costs are indicative and subject to:
- Exchange rates
- Local market conditions
- Supply chain factors
- Regional regulations
- Labor availability
- Material costs
Additional Considerations:
- Local certification requirements
- Regional maintenance standards
- Spare parts availability
- Warranty conditions
- Service life expectations
- Energy efficiency requirements
- Environmental regulations
- Local labor laws
Project Phase Analysis:
Demolition Phase:
- Preparation (5-7 days):
- Hoarding installation
- Service isolation
- Protection works
- Access establishment
- Removal Works (10-14 days):
- Car removal: 2-3 days
- Guide rail removal: 3-4 days
- Equipment removal: 4-5 days
- Shaft cleaning: 2-3 days
Installation Phase:
- Structural Works (2-3 weeks):
- Shaft modifications
- Landing preparations
- Support steel installation
- Pit modifications
- Lift Installation (6-8 weeks):
- Guide rails: 5-7 days
- Car assembly: 8-10 days
- Machine room equipment: 5-7 days
- Controls installation: 7-9 days
- Doors and frames: 5-6 days
- Finishing Works (2-3 weeks):
- Landing finishes
- Car interior
- Signage
- Lighting
Testing and Commissioning:
- Initial Testing (7-10 days):
- Safety systems
- Emergency features
- Control systems
- Door operations
- Certification (5-7 days):
- Independent inspection
- Documentation review
- Compliance verification
- Handover preparation
Project Milestones:
Pre-Construction:
- Design approval: 4-6 weeks
- Material procurement: 12-16 weeks
- Planning approvals: 6-8 weeks
- Stakeholder engagement: 4-6 weeks
Construction Phase:
Week 1-2: Site establishment
Week 2-4: Demolition
Week 4-12: Installation
Week 12-14: Finishing
Week 14-16: Testing
Week 16-18: Commissioning
Note 1: Production rates are indicative only.
Note 2: Rates vary based on:
- Station complexity
- Access constraints
- Heritage requirements
- Operational impacts
- Interface requirements
Note 3: Duration calculation formula:
D = (BT Ă— CF Ă— AF) + TC, where:
- D = Total duration
- BT = Base time
- CF = Complexity factor (1.0-1.6)
- AF = Access factor (1.0-1.4)
- TC = Testing constant
Influencing Factors:
- Station operations
- Heritage constraints
- Service relocations
- Weather protection
- Material delivery
- Working hours
- Safety requirements
- Passenger management
- Testing requirements
- Certification process
Risk Mitigation:
- Access Management:
- Alternative paths
- Temporary facilities
- Clear signage
- Customer assistance
- Safety Controls:
- Work zone isolation
- Dust control
- Noise management
- Public protection
- Quality Assurance:
- Regular inspections
- Progress monitoring
- Documentation control
- Compliance checking
Other production rates – Indicative only
- RAIL INDUSTRY PRODUCTION RATES COMPREHENSIVE TABLE
-
- Ballast Cleaning Operations Analysis
- Canopy Installation Analysis for Aerial Concourses
- Cut and Fill Production Rates in Railway Station Construction
- CSR (Cable Service Routes) Installation Analysis
- Demolition Works Analysis for Railway Infrastructure
- Electrical Overlaps (OHW) 33kV Installation Analysis
- Elevated Service Access Platforms (ESAPs) for Stabling Yards Analysis
- Escalator Installation Analysis for Rail Stations
- Fence Installation Between Tracks Analysis (Live Corridor vs Possession Works)
- HDD Under Rail Tracks – 48-Hour Possession Analysis
- High-Speed Rail Construction Analysis
- Horizontal Directional Drilling (HDD)
- Lght Rail Construction Production Rates: Global Analysis
- Lift Replacement Projects Analysis
- Mechanical Gap Fillers Installation Analysis
- New Aerial Concourse Installation Analysis for Train Stations
- New Intercity Fleet (NIF) Platform Extension Projects Analysis
- Overhead Wire (OHW) Structure Installation Analysis
- Platform Extension Projects: Global Analysis
- Platform Marker Repainting Analysis
- Railway Sleeper Replacement Analysis
- Roadheader Production Rates in Underground Station Construction: Global Performance Analysis
- Screen Indicator Installation Analysis for Rail Stations
- Segregation Fence Installation Analysis Between Tracks
- Slab Track Construction in Railway Stations: Global Production Analysis
- Sound Barrier Installation Analysis Along Rail Corridors
- Stabling Yard Construction and Production Analysis
- Track Replacement in Railway Stations: Production Analysis
- Transport Access Program (TAP) Production Rates and Delivery Analysis
- Tunnel Boring Machine (TBM) Production Analysis and Performance Metrics
- Tunnel Membrane/Waterproofing Installation Analysis
- Under Line Crossing (ULX) Installation Analysis
- Underpass Access Construction Analysis for Train Stations
- Utilities Relocation in Railway Environments Analysis
- Water-Filled Traffic Barriers Installation Analysis