RAIL INDUSTRY PRODUCTION RATES COMPREHENSIVE TABLE

RAIL INDUSTRY PRODUCTION RATES COMPREHENSIVE TABLE

  1. CIVIL WORKS & EXCAVATION
Activity Unit Production Rate Equipment Notes
Bulk Excavation (Open) m³/day 800-1,200 50T Excavator Good access
Detailed Excavation m³/day 200-300 20T Excavator Around services
Rock Breaking m³/day 100-150 Hydraulic Breaker Medium strength
Station Box Excavation m³/day 400-600 Multiple Plant Urban environment
Backfilling m³/day 500-700 Compactor/Roller 98% compaction
  1. CONCRETE WORKS
Activity Unit Production Rate Labor Team Notes
Slab Pour m³/day 150-200 8-10 workers Level surface
Wall Pour m³/day 100-120 6-8 workers Standard height
Column Pour m³/day 40-50 4-6 workers Up to 6m height
Platform Edge m/day 25-30 8 workers Including finish
Precast Installation units/day 8-12 Crane + 6 workers Standard elements
  1. TRACK WORKS
Activity Unit Production Rate Equipment Notes
Track Laying (Ballasted) m/day 150-200 Track laying machine Main line
Track Laying (Slab) m/day 50-70 Multiple crews Station area
Ballast Installation m/day 300-400 Ballast train Including tamping
Rail Welding welds/day 15-20 Welding team Flash butt welding
Turnout Installation units/day 1-2 Multiple crews Complete install
  1. OHW (OVERHEAD WIRING)
Activity Unit Production Rate Equipment Notes
Mast Installation units/day 6-8 Mobile crane Including foundation
Wire Running m/day 400-500 Wiring unit Main line
Registration spans/day 8-10 EWP teams Including adjustment
Tensioning spans/day 6-8 Tensioning unit Final setup
  1. STRUCTURAL STEEL
Activity Unit Production Rate Equipment Notes
Steel Erection tonnes/day 8-12 100T crane Station structures
Roof Installation m²/day 200-250 Mobile crane Including purlins
Platform Canopy m/day 15-20 Multiple crews Complete system
Footbridge Install spans/day 1-2 Heavy crane Prefabricated
  1. MECHANICAL & ELECTRICAL
Activity Unit Production Rate Labor Team Notes
Cable Installation m/day 300-400 6 workers Main routes
Lighting Install units/day 15-20 4 workers Platform area
HVAC Ductwork m/day 20-25 6 workers Station areas
Equipment Install units/day 2-3 Specialist team Switchboards etc
  1. DEMOLITION
Activity Unit Production Rate Equipment Notes
Structure Demolition m³/day 150-200 30T excavator Progressive
Track Removal m/day 200-250 Multiple plant Including sleepers
Concrete Breaking m³/day 80-100 Breaker attach Reinforced
Steel Removal tonnes/day 20-25 Cutting team Including sorting
  1. TUNNELING
Activity Unit Production Rate Method Notes
TBM Advance m/day 15-20 EPB TBM Good ground
Roadheader m³/day 80-100 Medium rock Station cavern
Shotcrete m²/day 150-200 Robotic arm Primary lining
Rock Bolting bolts/day 40-50 Drilling rig Systematic
  1. FINISHING WORKS
Activity Unit Production Rate Labor Team Notes
Tiling m²/day 40-50 4 workers Platform area
Painting m²/day 200-250 3 workers Walls/ceiling
Handrail Install m/day 30-40 4 workers Standard system
Signage Install units/day 15-20 2 workers All types

Note 1: Production rates are indicative only and assume:

  • Good access conditions
  • Skilled labor teams
  • Appropriate equipment
  • Normal working hours
  • Standard specifications

Note 2: Factors affecting rates:

  • Site constraints
  • Weather conditions
  • Resource availability
  • Interface requirements
  • Safety requirements
  • Quality standards
  • Environmental controls

Note 3: Calculation basis:

  • 8-10 hour working day
  • Excluding setup/pack up
  • Including normal breaks
  • Standard efficiency factors
  • Typical urban conditions

 

Detailed specifications and subcategories.

  1. CIVIL WORKS & EXCAVATION (DETAILED)

BULK EXCAVATION

Activity Ground Type Production Rate Equipment Team Size Notes
Soft Soil Clay/Sand 1000-1200 m³/day 50T Excavator 3-4 Good access
Mixed Ground Clay/Gravel 800-1000 m³/day 50T Excavator 3-4 Some rock
Hard Ground Weathered Rock 500-700 m³/day 50T + Breaker 4-5 Regular breaking
Rock Sandstone 300-400 m³/day 50T + Rock Breaker 4-5 Hard rock

DETAILED EXCAVATION

Activity Condition Production Rate Equipment Team Size Notes
Service Trenches Open Area 80-100 m/day 13T Excavator 3-4 Clear area
Around Services Congested 40-60 m/day 8T Excavator 4-5 Hand dig support
Foundation Pits Standard 150-200 m³/day 20T Excavator 3-4 Square/rectangular
Drainage Lines Linear 60-80 m/day 13T Excavator 4-5 Including bedding
  1. CONCRETE WORKS (DETAILED)

SLAB CONSTRUCTION

Activity Type Production Rate Equipment Team Size Notes
Platform Slab Level 150-200 m³/day Pump/Vibrator 8-10 Including finish
Track Slab Rail corridor 100-120 m³/day Pump/Vibrator 10-12 Including rail seats
Building Base Standard 180-220 m³/day Pump/Vibrator 8-10 Flat slab
Suspended Slab Elevated 120-150 m³/day Pump/Vibrator 10-12 Including formwork

WALL CONSTRUCTION

Activity Type Production Rate Equipment Team Size Notes
Retaining Wall Standard 80-100 m³/day Crane/Pump 8-10 Including reinforcement
Station Wall Architectural 60-80 m³/day Crane/Pump 10-12 Including finish
Barrier Wall Slip formed 100-120 m/day Slip former 6-8 Linear production
Core Walls Complex 40-60 m³/day Crane/Pump 12-14 Including services

Would you like me to continue with more categories or focus on specific aspects of these?

  1. TRACK WORKS (DETAILED)

BALLASTED TRACK

Activity Type Production Rate Equipment Team Size Notes
Formation Prep Standard 400-500 m/day Grader/Roller 6-8 Including testing
Ballast Laying Main line 600-800 m/day Ballast train 8-10 Initial layer
Sleeper Laying Concrete 800-1000 m/day Track machine 10-12 Including spacing
Rail Installation CWR 600-800 m/day Rail train 12-14 Including clips
Final Tamping Main line 800-1000 m/day Tamper 4-6 Including alignment

SLAB TRACK

Activity Type Production Rate Equipment Team Size Notes
Base slab Standard 50-70 m/day Pump/Vibrator 10-12 Including reinforcement
Rail Seat Install Precise 80-100 m/day Survey/Manual 8-10 Including setting out
Rail Installation Station 100-120 m/day Crane/Manual 10-12 Including adjustment
Final Grouting Precision 150-200 m/day Grout pump 6-8 Including testing

 

  1. OHW (OVERHEAD WIRING) DETAILED

FOUNDATIONS & MASTS

Activity Type Production Rate Equipment Team Size Notes
Pile Foundations Bored 6-8/day Piling rig 6-8 Including concrete
Pad Foundations Cast in-situ 8-10/day Mobile crane 8-10 Including excavation
Mast Erection Standard 8-10/day 25T crane 6-8 Including alignment
Portal Installation Double track 3-4/day 50T crane 10-12 Complete assembly

WIRING INSTALLATION

Activity Type Production Rate Equipment Team Size Notes
Catenary Running Main line 800-1000m/day Wiring unit 10-12 Including pulleys
Contact Wire Precision 600-800m/day Wiring unit 12-14 Including registration
Registration Arms Standard 20-25/day EWP 6-8 Including adjustment
Tensioning Section 400-500m/day Tensioning unit 8-10 Final setup
  1. SIGNALLING INSTALLATION (DETAILED)

TRACKSIDE EQUIPMENT

Activity Type Production Rate Equipment Team Size Notes
Signal Installation Post mounted 2-3/day Hiab truck 6-8 Complete install
Track Circuit Double rail 200-250m/day Manual 4-6 Including bonding
Point Machine Standard 1-2/day Mobile crane 8-10 Including testing
Axle Counter Digital 4-5/day Manual 4-6 Including cable

CABLE INSTALLATION

Activity Type Production Rate Equipment Team Size Notes
Main Cable Route Tracksides 300-400m/day Cable trailer 8-10 Including troughing
Local Cable Equipment 150-200m/day Manual 4-6 Including termination
Fiber Optic Backbone 500-600m/day Specialist team 6-8 Including testing
Under Track Cross Boring 2-3/day Boring unit 6-8 Including pits
  1. STATION WORKS (DETAILED)

PLATFORM CONSTRUCTION

Activity Type Production Rate Equipment Team Size Notes
Base Structure Precast 15-20m/day 100T crane 10-12 Including backfill
Platform Surface In-situ 25-30m/day Pump/Finish 8-10 Including tactiles
Edge Elements Precast 30-35m/day 25T crane 6-8 Including alignment
Canopy Install Modular 20-25m/day Mobile crane 8-10 Complete system

STATION BUILDINGS

Activity Type Production Rate Equipment Team Size Notes
Steel Frame Main building 8-10T/day 200T crane 12-14 Including bracing
Floor Slabs Composite 200-250m²/day Pump/Finish 10-12 Including mesh
Roof Installation Standard 300-350m²/day Mobile crane 8-10 Including sealing
Cladding External 150-200m²/day EWP 6-8 Including flashings
  1. MECHANICAL & ELECTRICAL (DETAILED)

STATION SERVICES

Activity Type Production Rate Equipment Team Size Notes
Main Cable Routes Containment 100-120m/day Manual 6-8 Including brackets
Lighting Install Platform 15-20 units/day EWP 4-6 Including testing
HVAC Ductwork Main runs 25-30m/day Mobile lift 8-10 Including hangers
Fire Services Pipework 40-50m/day Mobile lift 6-8 Including testing

POWER SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
HV Cable Install Main feed 200-250m/day Cable unit 10-12 Including joints
Transformer Install Standard 1-2/day 100T crane 8-10 Including connection
Switchboard Install Main DB 1-2/day Forklift 6-8 Including termination
Emergency Power Generator 1 unit/2-3 days Mobile crane 8-10 Complete system
  1. TUNNELING OPERATIONS (DETAILED)

TBM OPERATIONS

Activity Ground Type Production Rate Equipment Team Size Notes
Soft Ground EPB Mode 15-20m/day EPB TBM 20-25 Including rings
Mixed Ground Variable 12-15m/day Dual Mode TBM 20-25 Including ground treatment
Hard Rock Open Mode 18-25m/day Hard Rock TBM 18-22 Good conditions
Station Break-in/out All Types 2-3m/day Mixed Methods 25-30 Including protection

ROADHEADER OPERATIONS

Activity Rock Strength Production Rate Equipment Team Size Notes
Soft Rock (<50MPa) Cavern 80-100m³/day 100T Machine 8-10 Good access
Medium Rock (50-100MPa) Cross Passage 60-80m³/day 100T Machine 8-10 Standard size
Hard Rock (>100MPa) Station 40-60m³/day 100T Machine 10-12 Including support
Precise Cutting Profile 30-40m³/day 100T Machine 10-12 Final trim
  1. STATION FIT-OUT (DETAILED)

ARCHITECTURAL FINISHES

Activity Type Production Rate Equipment Team Size Notes
Wall Cladding Standard 80-100m²/day Mobile lift 6-8 Including framing
Ceiling Systems Suspended 100-120m²/day Mobile scaffold 6-8 Including services
Floor Finishes Granite/Tile 40-50m²/day Manual 6-8 Including prep
Glazing Systems Facade 50-60m²/day Mobile crane 8-10 Including frames

PASSENGER FACILITIES

Activity Type Production Rate Equipment Team Size Notes
Escalator Install Standard 1 unit/2 weeks 100T crane 10-12 Complete install
Lift Installation 2-3 Stops 1 unit/3 weeks Tower crane 8-10 Including testing
Ticket Gates Standard 4-5 units/day Manual 6-8 Including commissioning
Information Systems Displays 6-8 units/day Mobile lift 4-6 Including testing
  1. TRACK SYSTEMS (DETAILED)

POINTS AND CROSSINGS

Activity Type Production Rate Equipment Team Size Notes
Turnout Install Standard 1 unit/weekend 100T crane 15-20 Complete assembly
Diamond Crossing Complex 1 unit/2 days 100T crane 18-22 Including approach
Switch Blade Set Replacement 1 set/shift Mobile crane 12-15 Including testing
Check Rail Installation 100-120m/day Manual 8-10 Including gauging

RAIL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Rail Stressing CWR 800-1000m/day Stressing unit 10-12 Including clipping
Rail Grinding Mainline 800-1000m/day Rail grinder 8-10 Both rails
Track Recording Geometry 15-20km/day Recording car 4-6 Including analysis
Ultrasonic Test Rail defect 3-4km/day Test unit 4-6 Both rails
  1. CIVIL STRUCTURES (DETAILED)

BRIDGE CONSTRUCTION

Activity Type Production Rate Equipment Team Size Notes
Pier Construction Standard 1 pier/2 weeks Tower crane 12-15 Including foundation
Deck Segments Precast 2-3 units/day 200T crane 15-18 Including stress
Steel Girders Composite 2-3 spans/week Heavy crane 15-20 Including deck
Bearing Install Elastomeric 4-6 units/day Mobile crane 8-10 Including grouting

RETAINING WALLS

Activity Type Production Rate Equipment Team Size Notes
Piled Wall Contiguous 8-10 piles/day Piling rig 10-12 Including cage
Panel Wall Precast 10-12 panels/day Mobile crane 8-10 Including backfill
L-Wall Units Standard 15-20m/day 25T crane 6-8 Including base
Soil Nailing Reinforcement 12-15 nails/day Drilling rig 6-8 Including shotcrete
  1. STATION ELECTRICAL SYSTEMS (DETAILED)

LOW VOLTAGE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Distribution Boards Main/Sub 1-2 units/day Manual 4-6 Including terminations
Cable Tray Install Main routes 40-50m/day Mobile lift 6-8 Including brackets
Small Power GPOs/DBs 15-20 points/day Manual 4-6 Including testing
Emergency Lighting Coverage 20-25 units/day Mobile lift 4-6 Including battery

HIGH VOLTAGE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
HV Cable Install Main feed 150-200m/day Cable winch 8-10 Including joints
Switchgear Install 11kV/33kV 1 unit/2-3 days 50T crane 8-10 Including testing
Transformer Room Complete 1 room/week Various 10-12 Including commission
Earth System Grid/Rods 100-150m/day Manual 6-8 Including testing
  1. COMMUNICATIONS SYSTEMS (DETAILED)

BACKBONE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Fiber Optic Cable Main routes 400-500m/day Cable drum 6-8 Including splicing
Equipment Rooms Fit-out 1 room/week Manual 8-10 Including racks
CCTV Install Platform/Concourse 8-10 cameras/day Mobile lift 4-6 Including testing
PA System Coverage 12-15 speakers/day Mobile lift 4-6 Including alignment

PASSENGER INFORMATION

Activity Type Production Rate Equipment Team Size Notes
Display Screens LED/LCD 4-6 units/day Mobile lift 4-6 Including network
Help Points Emergency 6-8 units/day Manual 4-6 Including testing
Ticket Machines Self-service 2-3 units/day Manual 4-6 Including commission
Way Finding Signage 15-20 units/day Various 4-6 Including fixing
  1. FIRE & LIFE SAFETY (DETAILED)

FIRE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Sprinkler Install Main runs 40-50m/day Mobile lift 6-8 Including heads
Fire Detection Sensors 25-30 units/day Mobile lift 4-6 Including testing
Hydrant System Coverage 2-3 units/day Manual 6-8 Including testing
Smoke Control Dampers 6-8 units/day Mobile lift 6-8 Including controls

EMERGENCY SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Emergency Lighting Coverage 20-25 units/day Mobile lift 4-6 Including battery
Exit Signs Illuminated 15-20 units/day Manual 4-6 Including wiring
Fire Doors Rated 4-5 units/day Manual 6-8 Including hardware
Emergency Exit Complete 1 route/week Various 8-10 Including signage
  1. MECHANICAL SYSTEMS (DETAILED)

HVAC SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Main Ductwork Galvanized 25-30m/day Mobile lift 8-10 Including hangers
AHU Installation Package unit 1 unit/2-3 days Crane 8-10 Including connections
VAV Boxes Distribution 4-5 units/day Mobile lift 6-8 Including controls
Chilled Water Pipework 30-40m/day Mobile lift 6-8 Including insulation

VENTILATION SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Tunnel Fans Main units 1 unit/2 days Crane 10-12 Including mounting
Smoke Extract Ductwork 20-25m/day Mobile lift 8-10 Including dampers
Platform Screen Doors 2-3 sets/day Mobile crane 10-12 Including controls
Ventilation Shaft Equipment 1 shaft/week Various 12-15 Complete system

 

 

 

  1. PLATFORM SCREEN DOORS (DETAILED)

INSTALLATION PHASES

Activity Type Production Rate Equipment Team Size Notes
Support Structure Main frame 20-25m/day Mobile crane 8-10 Including alignment
Door Units Full height 4-5 sets/day Manual/lift 10-12 Including guides
Control Systems Per platform 1 platform/week Manual 6-8 Including testing
Emergency Exits Fixed panels 6-8 units/day Manual 6-8 Including seals

COMMISSIONING

Activity Type Production Rate Equipment Team Size Notes
Door Testing Individual 10-12 doors/day Test equipment 4-6 Including adjustment
Interface Testing Signalling 1 platform/2 days Various 6-8 Including trains
Safety Systems Emergency 1 platform/day Test equipment 4-6 Including scenarios
Final Testing Complete 1 platform/2 days Various 8-10 Including documentation
  1. STATION VERTICAL TRANSPORTATION (DETAILED)

ESCALATOR INSTALLATION

Activity Type Production Rate Equipment Team Size Notes
Truss Install Standard 1 unit/2-3 days Heavy crane 12-15 Including alignment
Step Chain Assembly 1 unit/2 days Manual 8-10 Including adjustment
Balustrade Glass/SS 1 unit/2 days Manual 6-8 Including cleaning
Controls Complete 1 unit/2 days Manual 4-6 Including testing

LIFT INSTALLATION

Activity Type Production Rate Equipment Team Size Notes
Guide Rails Standard 2-3 floors/day Manual 6-8 Including brackets
Car Install Complete 1 unit/2 days Mobile crane 8-10 Including doors
Machine Room Equipment 1 room/3 days Various 6-8 Including controls
Testing Full system 1 unit/2 days Test weights 4-6 Including certification
  1. TRACK DRAINAGE (DETAILED)

UNDERGROUND DRAINAGE

Activity Type Production Rate Equipment Team Size Notes
Main Carrier Large dia. 20-25m/day Excavator 8-10 Including bedding
Track Drainage Standard 30-35m/day Mini excavator 6-8 Including connections
Pits Install Precast 4-5 units/day Mobile crane 6-8 Including levels
Pumping Station Complete 1 unit/week Various 10-12 Including commission

SURFACE DRAINAGE

Activity Type Production Rate Equipment Team Size Notes
Platform Edge Linear drain 40-50m/day Manual 6-8 Including grating
Catch Drains Formation 60-80m/day Excavator 6-8 Including lining
Culvert Install Box/Pipe 15-20m/day Crane 8-10 Including headwalls
Detention Tank Precast 1 unit/3 days Heavy crane 10-12 Including connections
  1. STATION FINISHES (DETAILED)

WALL FINISHES

Activity Type Production Rate Equipment Team Size Notes
Tiling Ceramic/Stone 30-40m²/day Manual 6-8 Including prep
Metal Cladding System 50-60m²/day Mobile lift 8-10 Including framing
Painting Standard 150-200m²/day Spray/Roll 4-6 Including prep
Feature Walls Custom 20-25m²/day Various 6-8 Including lighting

CEILING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Metal Panel Modular 80-100m²/day Mobile scaffold 6-8 Including grid
Linear Aluminum 60-70m²/day Mobile scaffold 6-8 Including supports
Bulkheads Custom 20-25m/day Mobile scaffold 6-8 Including access
Service Integration Coordination 40-50m²/day Various 8-10 Including testing

 

 

 

 

  1. PLATFORM & CONCOURSE FLOORING (DETAILED)

PLATFORM SURFACES

Activity Type Production Rate Equipment Team Size Notes
Granite Paving Heavy duty 35-45m²/day Manual 8-10 Including bedding
Tactile Install Warning/Direct 50-60m/day Manual 6-8 Including adhesive
Edge Strips Safety 80-100m/day Manual 4-6 Including sealant
Anti-slip Treatment Coating 200-250m²/day Spray 4-6 Including prep

CONCOURSE FLOORING

Activity Type Production Rate Equipment Team Size Notes
Terrazzo Large areas 40-50m²/day Power float 8-10 Including polish
Resin Flooring Seamless 150-200m²/day Power trowel 6-8 Including primer
Raised Access Modular 100-120m²/day Manual 6-8 Including pedestals
Movement Joints Expansion 30-40m/day Manual 4-6 Including sealant
  1. STATION EXTERNAL WORKS (DETAILED)

PAVING & ROADS

Activity Type Production Rate Equipment Team Size Notes
Block Paving Pedestrian 80-100m²/day Manual 8-10 Including base
Asphalt Vehicle areas 400-500m²/day Paver 10-12 Including rolling
Kerbing Precast 100-120m/day Manual 6-8 Including haunching
Line Marking Standard 500-600m/day Machine 4-6 Including setting out

LANDSCAPING

Activity Type Production Rate Equipment Team Size Notes
Topsoiling Prepared 400-500m²/day Excavator 6-8 Including grading
Tree Planting Mature 8-10 trees/day Mobile crane 6-8 Including pit prep
Irrigation System 200-250m/day Manual 6-8 Including testing
Street Furniture Mixed 10-12 units/day Mobile crane 6-8 Including fixing
  1. STATION SECURITY SYSTEMS (DETAILED)

ACCESS CONTROL

Activity Type Production Rate Equipment Team Size Notes
Card Readers Standard 8-10 units/day Manual 4-6 Including wiring
Security Doors Heavy duty 2-3 units/day Manual 6-8 Including hardware
Turnstiles Full height 2-3 units/day Mobile crane 8-10 Including controls
Barriers Vehicle 1-2 units/day Mobile crane 6-8 Including commission

SURVEILLANCE

Activity Type Production Rate Equipment Team Size Notes
CCTV Cameras Fixed/PTZ 10-12 units/day Mobile lift 4-6 Including setup
Control Room Equipment 1 room/week Manual 8-10 Including monitors
Recording System Network 1 system/3 days Manual 4-6 Including storage
Analytics Setup Software 15-20 cameras/day Manual 2-4 Including testing
  1. STATION WAYFINDING (DETAILED)

SIGNAGE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Directional Wall mounted 15-20 units/day Mobile lift 4-6 Including templates
Suspended Ceiling hung 10-12 units/day Mobile lift 6-8 Including supports
Platform Track side 8-10 units/day Mobile lift 6-8 Including lighting
Digital Dynamic 4-5 units/day Various 6-8 Including network

PASSENGER INFORMATION

Activity Type Production Rate Equipment Team Size Notes
LCD Displays Information 6-8 units/day Mobile lift 6-8 Including cabling
Maps Static 10-12 units/day Manual 4-6 Including frames
Touch Screens Interactive 3-4 units/day Manual 4-6 Including software
Emergency Info Statutory 20-25 units/day Manual 4-6 Including fixing

 

  1. STATION BUILDING SERVICES (DETAILED)

WATER SERVICES

Activity Type Production Rate Equipment Team Size Notes
Main Supply Large dia. 30-40m/day Excavator 8-10 Including testing
Distribution Internal 50-60m/day Mobile lift 6-8 Including insulation
Hot Water System 40-50m/day Manual 6-8 Including cylinders
Metering Smart 3-4 units/day Manual 4-6 Including commission

WASTE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Soil & Waste Main runs 35-45m/day Mobile lift 6-8 Including vents
Trade Waste Grease 25-30m/day Manual 6-8 Including traps
Storm Water Roof 40-50m/day Mobile lift 6-8 Including sumps
Pumping Station 1 unit/2 days Mobile crane 8-10 Including controls
  1. PLATFORM EDGE WORKS (DETAILED)

EDGE PROTECTION

Activity Type Production Rate Equipment Team Size Notes
Copings Precast 40-50m/day Mobile crane 8-10 Including bedding
Safety Line Yellow 100-120m/day Manual 4-6 Including prep
Tactile Strip Warning 80-100m/day Manual 6-8 Including adhesive
Edge Lighting LED 50-60m/day Manual 6-8 Including wiring

PLATFORM FURNITURE

Activity Type Production Rate Equipment Team Size Notes
Seating Standard 8-10 units/day Manual 4-6 Including fixing
Bins Modular 12-15 units/day Manual 4-6 Including anchors
Barriers Safety 30-40m/day Manual 6-8 Including posts
Lean Rails Stainless 40-50m/day Manual 6-8 Including fixings
  1. STATION TESTING & COMMISSIONING (DETAILED)

SYSTEMS TESTING

Activity Type Production Rate Equipment Team Size Notes
Power Systems HV/LV 1 system/2 days Test equipment 8-10 Including certification
Communications Network 1 system/3 days Test gear 6-8 Including protocols
Fire Systems Complete 1 system/2 days Test equipment 8-10 Including scenarios
Security Integration 1 system/2 days Test gear 6-8 Including verification

INTEGRATED TESTING

Activity Type Production Rate Equipment Team Size Notes
Scenario Testing Emergency 5-6 scenarios/day Various 12-15 Including documentation
Interface Tests Systems 3-4 systems/day Test gear 10-12 Including verification
Performance Tests Load 2-3 tests/day Various 8-10 Including monitoring
Documentation As-built 1 system/day Manual 4-6 Including handover
  1. STATION CLEANING & HANDOVER (DETAILED)

FINAL CLEANING

Activity Type Production Rate Equipment Team Size Notes
Public Areas Deep clean 500-600m²/day Industrial 8-10 Including equipment
Technical Rooms Specialist 200-250m²/day Manual 6-8 Including verification
External Areas Pressure wash 600-700m²/day Pressure wash 6-8 Including access
Glass/Facades High level 300-400m²/day Access equip 6-8 Including certification

HANDOVER PREPARATION

Activity Type Production Rate Equipment Team Size Notes
Snag Lists Resolution 20-25 items/day Various 6-8 Including verification
Asset Tagging Labels/RFID 100-120 items/day Manual 4-6 Including database
O&M Manuals Compilation 1 system/day Manual 2-4 Including review
Training Staff 2-3 sessions/day Various 4-6 Including assessment

 

  1. STATION POWER DISTRIBUTION (DETAILED)

MAIN SWITCHBOARDS

Activity Type Production Rate Equipment Team Size Notes
HV Switchgear 11kV/33kV 1 panel/day Heavy crane 10-12 Including testing
LV Boards Main DB 1-2 units/day Forklift 8-10 Including terminations
UPS Systems Critical 1 system/2 days Forklift 6-8 Including batteries
Generator Emergency 1 unit/3 days Heavy crane 10-12 Including fuel system

CABLE INSTALLATION

Activity Type Production Rate Equipment Team Size Notes
HV Cables Main feed 150-200m/day Cable winch 10-12 Including joints
LV Mains Distribution 200-250m/day Cable drum 8-10 Including terminations
Control Cables Multicore 300-400m/day Manual 6-8 Including labeling
Cable Ladder Support 50-60m/day Mobile lift 6-8 Including brackets
  1. PLATFORM VENTILATION (DETAILED)

TUNNEL VENTILATION

Activity Type Production Rate Equipment Team Size Notes
Main Fans Axial 1 unit/2 days Heavy crane 12-15 Including mounting
Dampers Motorized 3-4 units/day Mobile lift 8-10 Including controls
Ductwork Large dia. 15-20m/day Mobile crane 10-12 Including supports
Monitoring Sensors 8-10 units/day Manual 4-6 Including calibration

ENVIRONMENTAL CONTROL

Activity Type Production Rate Equipment Team Size Notes
Air Handling Units 1 unit/2 days Mobile crane 10-12 Including connections
Cooling Chillers 1 unit/3 days Heavy crane 12-15 Including pipework
Air Distribution Ductwork 25-30m/day Mobile lift 8-10 Including diffusers
BMS Control System 1 zone/day Manual 4-6 Including programming
  1. STATION FIRE ENGINEERING (DETAILED)

FIRE SUPPRESSION

Activity Type Production Rate Equipment Team Size Notes
Sprinkler Mains Large dia. 35-40m/day Mobile lift 8-10 Including valves
Branch Lines Distribution 50-60m/day Mobile lift 6-8 Including heads
Gas Systems Clean agent 1 room/2 days Various 8-10 Including detection
Pump Sets Fire duty 1 set/3 days Mobile crane 10-12 Including testing

SMOKE CONTROL

Activity Type Production Rate Equipment Team Size Notes
Extract Fans Emergency 1 unit/2 days Heavy crane 10-12 Including controls
Smoke Barriers Automatic 20-25m/day Mobile lift 8-10 Including motors
Pressurization Stairwells 1 system/3 days Various 8-10 Including testing
Control System Integration 1 zone/day Manual 6-8 Including scenarios
  1. STATION TELECOMMUNICATIONS (DETAILED)

RADIO SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Base Stations Coverage 1-2 units/day Mobile lift 6-8 Including alignment
Antenna Systems Distributed 4-5 units/day Mobile lift 6-8 Including testing
Feeder Cable Main runs 200-250m/day Cable drum 8-10 Including supports
Coverage Test Verification 1 level/day Test gear 4-6 Including mapping

DATA NETWORKS

Activity Type Production Rate Equipment Team Size Notes
Core Switches Main rooms 2-3 units/day Manual 6-8 Including config
Fiber Backbone Distribution 300-400m/day Manual 6-8 Including splicing
Access Points Wi-Fi 8-10 units/day Mobile lift 4-6 Including setup
Network Test Performance 1 system/day Test gear 4-6 Including certification

 

  1. STATION ACCESS CONTROL (DETAILED)

TICKET GATES

Activity Type Production Rate Equipment Team Size Notes
Gate Arrays Standard 4-5 gates/day Manual 8-10 Including power/data
Wide Gates DDA 2-3 gates/day Manual 6-8 Including testing
Emergency Gates Break out 3-4 units/day Manual 6-8 Including alarms
Control System Integration 1 array/day Test gear 4-6 Including commission

STAFF ACCESS

Activity Type Production Rate Equipment Team Size Notes
Card Readers Proximity 10-12 units/day Manual 4-6 Including wiring
Biometric Fingerprint 6-8 units/day Manual 4-6 Including enrollment
Security Doors Controlled 2-3 units/day Manual 6-8 Including hardware
Intercom Video 8-10 units/day Manual 4-6 Including testing
  1. PLATFORM SCREEN DOORS MAINTENANCE ACCESS (DETAILED)

ACCESS SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Service Gates Maintenance 3-4 units/day Manual 6-8 Including interlocks
Access Platforms Temporary 15-20m/day Mobile lift 8-10 Including handrails
Safety Systems Fall arrest 25-30m/day Manual 6-8 Including certification
Emergency Exit Break glass 6-8 units/day Manual 4-6 Including testing

CONTROL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Key Switches Override 10-12 units/day Manual 4-6 Including wiring
Status Indicators LED 15-20 units/day Manual 4-6 Including testing
Interface Units Control 4-5 units/day Manual 6-8 Including programming
Emergency Stop E-Stop 8-10 units/day Manual 4-6 Including verification
  1. STATION ASSET MANAGEMENT SYSTEMS (DETAILED)

ASSET TAGGING

Activity Type Production Rate Equipment Team Size Notes
Equipment Tags RFID/QR 100-120 units/day Manual 4-6 Including database
Location Tags Spatial 80-100 units/day Manual 4-6 Including mapping
Service Points Maintenance 50-60 units/day Manual 4-6 Including registration
Critical Assets Priority 40-50 units/day Manual 6-8 Including documentation

MONITORING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Sensors Condition 15-20 units/day Manual 6-8 Including calibration
Data Loggers Remote 8-10 units/day Manual 4-6 Including setup
SCADA Points Integration 20-25 points/day Manual 6-8 Including programming
Analytics Setup 1 system/2 days Manual 4-6 Including training
  1. STATION ENVIRONMENTAL SYSTEMS (DETAILED)

ENERGY MANAGEMENT

Activity Type Production Rate Equipment Team Size Notes
Meters Smart 6-8 units/day Manual 4-6 Including networking
LED Lighting Control 30-40 units/day Mobile lift 6-8 Including programming
Solar Panels Renewable 20-25 panels/day Mobile crane 8-10 Including connections
BMS Points Monitoring 15-20 points/day Manual 4-6 Including integration

WASTE MANAGEMENT

Activity Type Production Rate Equipment Team Size Notes
Sorting Bins Recycling 10-12 units/day Manual 4-6 Including signage
Compactors Waste 1 unit/2 days Mobile crane 6-8 Including commissioning
Collection Points Service 3-4 units/day Manual 4-6 Including access
Water Recycling Grey water 1 system/3 days Various 8-10 Including treatment

 

 

 

  1. STATION PLATFORM EDGE LIGHTING (DETAILED)

UNDER PLATFORM LIGHTING

Activity Type Production Rate Equipment Team Size Notes
LED Strips Continuous 60-80m/day Manual 6-8 Including diffusers
Power Supply Units 8-10 units/day Manual 4-6 Including testing
Control Units Dimming 6-8 units/day Manual 4-6 Including programming
Emergency Feed Backup 50-60m/day Manual 6-8 Including testing

EDGE WARNING LIGHTS

Activity Type Production Rate Equipment Team Size Notes
Warning Strip LED 40-50m/day Manual 6-8 Including mounting
Train Approach Indicators 10-12 units/day Manual 6-8 Including sensors
Control System Integration 1 platform/day Test gear 4-6 Including verification
Emergency Mode Override 1 system/day Manual 4-6 Including scenarios
  1. STATION PUBLIC ADDRESS SYSTEMS (DETAILED)

SPEAKER SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Platform Speakers Directional 15-20 units/day Mobile lift 6-8 Including alignment
Concourse Speakers Ceiling 20-25 units/day Mobile lift 6-8 Including zoning
Emergency Speakers Protected 12-15 units/day Mobile lift 6-8 Including testing
Ambient Sensors Noise 8-10 units/day Manual 4-6 Including calibration

CONTROL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Amplifiers Rack mount 4-5 units/day Manual 4-6 Including setup
Zone Controllers Digital 3-4 units/day Manual 4-6 Including programming
Message Store Digital 1 system/day Manual 4-6 Including recording
Interface Units Network 2-3 units/day Manual 4-6 Including integration
  1. STATION CCTV SYSTEMS (DETAILED)

CAMERA INSTALLATION

Activity Type Production Rate Equipment Team Size Notes
Fixed Cameras HD/4K 12-15 units/day Mobile lift 6-8 Including focusing
PTZ Cameras High speed 8-10 units/day Mobile lift 6-8 Including setup
Specialty Cameras Thermal/LPR 6-8 units/day Mobile lift 6-8 Including calibration
Analytics Setup AI enabled 10-12 units/day Manual 4-6 Including training

RECORDING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
NVR Install Network 2-3 units/day Manual 4-6 Including configuration
Storage Arrays RAID 1-2 units/day Manual 4-6 Including setup
Workstations Operator 4-5 units/day Manual 4-6 Including software
Video Wall Display 1 system/2 days Mobile lift 8-10 Including calibration
  1. STATION INFORMATION SYSTEMS (DETAILED)

PASSENGER INFORMATION

Activity Type Production Rate Equipment Team Size Notes
LED Displays Large format 3-4 units/day Mobile lift 8-10 Including mounting
LCD Screens Information 6-8 units/day Mobile lift 6-8 Including network
Touch Kiosks Interactive 4-5 units/day Manual 6-8 Including testing
Journey Planners Digital 3-4 units/day Manual 4-6 Including software

REAL-TIME SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Train Info Displays 5-6 units/day Mobile lift 6-8 Including data feed
Platform Info Next train 8-10 units/day Mobile lift 6-8 Including sensors
Service Updates System 1 system/day Manual 4-6 Including integration
Emergency Info Override 1 system/day Manual 4-6 Including testing

 

 

 

  1. STATION FIRE DETECTION & ALARM (DETAILED)

DETECTION SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Smoke Detectors Addressable 25-30 units/day Mobile lift 6-8 Including testing
Heat Detectors Rate of rise 30-35 units/day Mobile lift 6-8 Including zoning
Beam Detectors Long range 4-6 units/day Mobile lift 6-8 Including alignment
Aspirating Systems VESDA 1 system/2 days Various 8-10 Including pipework

ALARM SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Call Points Break glass 20-25 units/day Manual 4-6 Including testing
Sounders Addressable 15-20 units/day Mobile lift 6-8 Including audibility
Beacons Visual 20-25 units/day Mobile lift 6-8 Including coverage
Interface Units Control 8-10 units/day Manual 4-6 Including programming
  1. STATION EMERGENCY LIGHTING (DETAILED)

EMERGENCY LUMINAIRES

Activity Type Production Rate Equipment Team Size Notes
Exit Signs LED 25-30 units/day Mobile lift 6-8 Including testing
Escape Route Maintained 30-35 units/day Mobile lift 6-8 Including circuits
Open Area Non-maintained 20-25 units/day Mobile lift 6-8 Including coverage
High Risk Area Enhanced 15-20 units/day Mobile lift 8-10 Including backup

CENTRAL BATTERY

Activity Type Production Rate Equipment Team Size Notes
Battery Units Static 2-3 units/day Forklift 8-10 Including connection
Distribution Circuits 200-250m/day Mobile lift 6-8 Including testing
Monitoring System 1 system/day Manual 4-6 Including setup
Testing System Automatic 1 system/2 days Manual 4-6 Including programming
  1. STATION EARTHING & BONDING (DETAILED)

MAIN EARTHING

Activity Type Production Rate Equipment Team Size Notes
Earth Rods Deep driven 6-8 units/day Specialist rig 6-8 Including testing
Earth Mats Grid system 100-150m²/day Excavator 8-10 Including backfill
Main Bonds Heavy duty 15-20 points/day Manual 6-8 Including terminals
Test Points Access 10-12 units/day Manual 4-6 Including labeling

SUPPLEMENTARY BONDING

Activity Type Production Rate Equipment Team Size Notes
Metallic Services Water/Gas 30-40 points/day Manual 4-6 Including labels
Cable Trays Continuous 200-250m/day Mobile lift 6-8 Including clips
Structural Steel Connections 25-30 points/day Mobile lift 6-8 Including testing
Lightning Protection System 1 system/3 days Various 8-10 Including terminals
  1. STATION BUILDING MANAGEMENT SYSTEM (DETAILED)

FIELD DEVICES

Activity Type Production Rate Equipment Team Size Notes
Temperature Sensors Space/Duct 20-25 units/day Manual 4-6 Including calibration
Pressure Sensors Air/Water 15-20 units/day Manual 4-6 Including setup
Flow Meters Various 8-10 units/day Manual 6-8 Including commissioning
CO2 Sensors Air quality 12-15 units/day Manual 4-6 Including testing

CONTROL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Controllers DDC 4-5 units/day Manual 6-8 Including programming
Network Points Integration 15-20 points/day Manual 4-6 Including testing
Graphics Interface 2-3 screens/day Manual 2-4 Including setup
Trend Logging Setup 30-40 points/day Manual 2-4 Including verification

 

 

 

  1. STATION PLATFORM DRAINAGE (DETAILED)

LINEAR DRAINAGE

Activity Type Production Rate Equipment Team Size Notes
Channel Drains Heavy duty 30-35m/day Manual 6-8 Including bedding
Gratings Load rated 40-45m/day Manual 4-6 Including fixing
Connection Points Inspection 6-8 units/day Manual 6-8 Including sealing
Fall Protection Safety mesh 50-60m/day Manual 4-6 Including clips

SUMP SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Sump Pits Precast 2-3 units/day Mobile crane 8-10 Including excavation
Pump Sets Submersible 1-2 sets/day Mobile crane 6-8 Including controls
Rising Mains Pressure pipe 40-50m/day Manual 6-8 Including testing
Control Panels Automation 2-3 units/day Manual 4-6 Including programming
  1. STATION PLATFORM HEATING (DETAILED)

HEATING ELEMENTS

Activity Type Production Rate Equipment Team Size Notes
Heat Mats Electric 100-120m²/day Manual 6-8 Including testing
Control Sensors Temperature 15-20 units/day Manual 4-6 Including calibration
Power Supply Distribution 4-5 units/day Manual 6-8 Including protection
Monitoring System 1 system/day Manual 4-6 Including setup

CONTROL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Zone Controllers Digital 6-8 units/day Manual 4-6 Including programming
Weather Stations Sensors 2-3 units/day Mobile lift 6-8 Including setup
Interface Units BMS 4-5 units/day Manual 4-6 Including integration
Energy Meters Smart 8-10 units/day Manual 4-6 Including verification
  1. STATION PLATFORM VENTILATION (DETAILED)

AIR MOVEMENT

Activity Type Production Rate Equipment Team Size Notes
Jet Fans Reversible 2-3 units/day Mobile crane 8-10 Including mounting
Air Curtains Entrance 3-4 units/day Mobile lift 6-8 Including controls
Extract Fans General 4-5 units/day Mobile lift 6-8 Including ductwork
Dampers Motorized 6-8 units/day Mobile lift 6-8 Including actuators

MONITORING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Air Quality Sensors 10-12 units/day Manual 4-6 Including calibration
Flow Meters Airflow 8-10 units/day Manual 4-6 Including setup
Temperature Monitoring 15-20 units/day Manual 4-6 Including testing
Control System Integration 1 system/day Manual 6-8 Including programming
  1. STATION PLATFORM LIGHTING (DETAILED)

GENERAL LIGHTING

Activity Type Production Rate Equipment Team Size Notes
Main Lights LED Linear 40-50m/day Mobile lift 6-8 Including mounting
Feature Lights Accent 15-20 units/day Mobile lift 6-8 Including focus
Emergency Integrated 25-30 units/day Mobile lift 6-8 Including testing
Control Gear DALI 20-25 units/day Manual 4-6 Including addressing

CONTROL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Daylight Sensors Photocell 10-12 units/day Mobile lift 4-6 Including setup
Motion Sensors PIR 15-20 units/day Mobile lift 4-6 Including testing
Scene Setting Controllers 4-5 units/day Manual 4-6 Including programming
Time Control System 1 system/day Manual 4-6 Including schedules

 

 

  1. STATION PLATFORM SCREEN DOORS (DETAILED)

DOOR SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Fixed Screens Glass panels 8-10 units/day Mobile crane 10-12 Including alignment
Sliding Doors Automated 6-8 sets/day Mobile crane 12-14 Including motors
Emergency Exits Manual 4-5 units/day Mobile lift 8-10 Including hardware
End Screens Terminal 2-3 units/day Mobile crane 8-10 Including fixing

CONTROL INTEGRATION

Activity Type Production Rate Equipment Team Size Notes
Door Controllers PLC based 4-5 units/day Manual 6-8 Including programming
Train Interface Sensors 8-10 units/day Manual 6-8 Including calibration
Safety Systems Monitoring 1 platform/day Test gear 8-10 Including verification
HMI Setup Operator 2-3 units/day Manual 4-6 Including configuration
  1. STATION ESCALATOR INSTALLATION (DETAILED)

STRUCTURAL WORKS

Activity Type Production Rate Equipment Team Size Notes
Truss Install Main structure 1 unit/3 days Heavy crane 12-15 Including alignment
Support Steel Secondary 1 set/2 days Mobile crane 8-10 Including fixing
Cladding Decorative 1 unit/2 days Mobile lift 6-8 Including panels
Landing Plates Transition 2-3 sets/day Manual 6-8 Including adjustment

MECHANICAL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Drive System Main motor 1 unit/day Mobile crane 8-10 Including alignment
Step Chain Assembly 1 unit/2 days Chain block 8-10 Including tension
Steps Install Individual 30-40 steps/day Manual 8-10 Including rollers
Handrail System Complete 1 unit/day Manual 6-8 Including drive
  1. STATION LIFT INSTALLATION (DETAILED)

SHAFT WORKS

Activity Type Production Rate Equipment Team Size Notes
Guide Rails Main rails 2-3 floors/day Manual 6-8 Including brackets
Landing Doors Complete 2-3 sets/day Manual 6-8 Including frames
Buffer Install Safety 2 sets/day Mobile crane 6-8 Including fixing
Pit Equipment Various 1 set/day Manual 6-8 Including ladders

LIFT CAR & SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Car Install Complete 1 unit/2 days Tower crane 8-10 Including interior
Machine Room Equipment 1 room/3 days Mobile crane 8-10 Including controls
Roping System Installation 1 system/day Winch 6-8 Including tension
Control System Programming 1 unit/day Manual 4-6 Including testing
  1. STATION TICKETING SYSTEMS (DETAILED)

TICKET VENDING

Activity Type Production Rate Equipment Team Size Notes
TVM Install Full service 2-3 units/day Manual 6-8 Including network
Top-up Machines Simple 4-5 units/day Manual 4-6 Including testing
Card Readers Contactless 8-10 units/day Manual 4-6 Including setup
Queue Systems Management 1 system/day Various 6-8 Including sensors

BACK OFFICE

Activity Type Production Rate Equipment Team Size Notes
Server Room Equipment 1 room/3 days Manual 6-8 Including racks
Network Setup Infrastructure 1 system/2 days Manual 4-6 Including testing
Database Configuration 1 system/day Manual 4-6 Including migration
Reporting System 1 system/day Manual 2-4 Including training

 

 

 

  1. STATION SECURITY SYSTEMS (DETAILED)

ACCESS CONTROL

Activity Type Production Rate Equipment Team Size Notes
Card Readers Proximity 12-15 units/day Manual 4-6 Including wiring
Security Gates Turnstiles 2-3 units/day Mobile crane 8-10 Including setup
Biometric Scanners 6-8 units/day Manual 4-6 Including enrollment
Door Controllers Local 8-10 units/day Manual 4-6 Including programming

INTRUSION DETECTION

Activity Type Production Rate Equipment Team Size Notes
PIR Sensors Motion 15-20 units/day Mobile lift 4-6 Including testing
Door Contacts Magnetic 20-25 units/day Manual 4-6 Including alignment
Glass Break Acoustic 12-15 units/day Manual 4-6 Including calibration
Control Panels Zoned 2-3 units/day Manual 6-8 Including programming
  1. STATION PASSENGER COUNTING (DETAILED)

COUNTING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Gate Sensors Infrared 10-12 units/day Manual 4-6 Including calibration
Overhead Sensors 3D Analytics 6-8 units/day Mobile lift 6-8 Including setup
Platform Edge Detection 20-25m/day Manual 6-8 Including testing
Data Collection Units 4-5 units/day Manual 4-6 Including network

ANALYSIS SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Servers Processing 1-2 units/day Manual 4-6 Including setup
Software Installation 1 system/day Manual 2-4 Including config
Reporting Setup 1 system/day Manual 2-4 Including templates
Integration Interface 1 system/2 days Manual 4-6 Including testing
  1. STATION QUEUE MANAGEMENT (DETAILED)

QUEUE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Barrier Posts Retractable 20-25 units/day Manual 4-6 Including setup
Digital Display LED 6-8 units/day Mobile lift 6-8 Including power
Ticket Dispensers Queue 4-5 units/day Manual 4-6 Including network
Sensors Monitoring 10-12 units/day Manual 4-6 Including calibration

MANAGEMENT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Control Units Local 2-3 units/day Manual 4-6 Including setup
Display Boards Information 4-5 units/day Mobile lift 6-8 Including wiring
Staff Stations Control 3-4 units/day Manual 4-6 Including training
Analytics Software 1 system/day Manual 2-4 Including configuration
  1. STATION HELP POINT SYSTEMS (DETAILED)

HELP POINTS

Activity Type Production Rate Equipment Team Size Notes
Main Units Emergency 6-8 units/day Manual 6-8 Including mounting
Information Points General 8-10 units/day Manual 4-6 Including network
Video Units Integrated 4-6 units/day Manual 6-8 Including testing
Hearing Loops Induction 10-12 units/day Manual 4-6 Including calibration

CONTROL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Control Room Equipment 1 room/3 days Manual 8-10 Including furniture
Recording System 1 system/day Manual 4-6 Including storage
Interface Emergency 1 system/2 days Manual 4-6 Including testing
Monitoring Software 1 system/day Manual 4-6 Including training

 

  1. STATION PLATFORM SEATING (DETAILED)

FIXED SEATING

Activity Type Production Rate Equipment Team Size Notes
Standard Benches Stainless 8-10 units/day Manual 4-6 Including anchoring
Priority Seating Special 6-8 units/day Manual 4-6 Including signage
Perch Seats Lean rails 12-15 units/day Manual 4-6 Including fixing
Anti-vandal Hardened 6-8 units/day Manual 6-8 Including security fixings

MODULAR SEATING

Activity Type Production Rate Equipment Team Size Notes
Beam Seating Multi-seat 4-5 units/day Manual 6-8 Including assembly
Charging Points Integrated 6-8 units/day Manual 4-6 Including power
Custom Units Branded 3-4 units/day Mobile lift 6-8 Including lighting
Accessibility Spaces 8-10 areas/day Manual 4-6 Including markings
  1. STATION WASTE MANAGEMENT (DETAILED)

WASTE COLLECTION

Activity Type Production Rate Equipment Team Size Notes
Bins Installation Standard 15-20 units/day Manual 4-6 Including anchoring
Recycling Points Sorted 8-10 units/day Manual 6-8 Including signage
Compactors Large 1 unit/2 days Mobile crane 8-10 Including services
Collection Points Service 2-3 areas/day Manual 6-8 Including access

MANAGEMENT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Level Sensors Smart 12-15 units/day Manual 4-6 Including setup
Control System Monitoring 1 system/day Manual 4-6 Including network
Collection Routes Planning 1 system/day Manual 2-4 Including mapping
Reporting Software 1 system/day Manual 2-4 Including training
  1. STATION CLEANING EQUIPMENT (DETAILED)

FIXED EQUIPMENT

Activity Type Production Rate Equipment Team Size Notes
Pressure Washers Wall mount 3-4 units/day Manual 6-8 Including plumbing
Hose Reels Service 6-8 units/day Manual 4-6 Including water supply
Storage Units Equipment 4-5 units/day Manual 4-6 Including shelving
Chemical Store Secure 1-2 units/day Manual 6-8 Including ventilation

MOBILE EQUIPMENT

Activity Type Production Rate Equipment Team Size Notes
Floor Scrubbers Ride-on 2-3 units/day Manual 4-6 Including charging
Vacuum Systems Industrial 3-4 units/day Manual 4-6 Including testing
Cleaning Carts Standard 8-10 units/day Manual 4-6 Including assembly
Storage Areas Designated 2-3 areas/day Manual 6-8 Including setup
  1. STATION RETAIL SERVICES (DETAILED)

RETAIL UNITS

Activity Type Production Rate Equipment Team Size Notes
Kiosk Shell Standard 1 unit/2 days Mobile crane 8-10 Including services
Shop Fronts Glazed 1 unit/day Mobile lift 6-8 Including security
Vending Areas Multiple 1 area/day Manual 6-8 Including power
Service Points Utilities 2-3 points/day Manual 4-6 Including testing

INFRASTRUCTURE

Activity Type Production Rate Equipment Team Size Notes
Power Supply Distribution 3-4 units/day Manual 6-8 Including metering
Data Points Network 8-10 points/day Manual 4-6 Including testing
Water Supply Metered 2-3 points/day Manual 6-8 Including isolation
Drainage Waste 2-3 points/day Manual 6-8 Including connection

 

  1. STATION ADVERTISING SYSTEMS (DETAILED)

DIGITAL DISPLAYS

Activity Type Production Rate Equipment Team Size Notes
LED Screens Large format 2-3 units/day Mobile crane 8-10 Including power/data
Digital Posters Interactive 4-5 units/day Mobile lift 6-8 Including network
Video Walls Multiple 1 wall/2 days Mobile lift 8-10 Including calibration
Media Players Control 6-8 units/day Manual 4-6 Including programming

STATIC DISPLAYS

Activity Type Production Rate Equipment Team Size Notes
Light Boxes Backlit 6-8 units/day Mobile lift 6-8 Including electrical
Poster Frames Standard 10-12 units/day Manual 4-6 Including mounting
Banner Systems Large 3-4 units/day Mobile lift 6-8 Including tensioning
Wayfinding Integration 8-10 units/day Manual 4-6 Including graphics
  1. STATION WEATHER PROTECTION (DETAILED)

PLATFORM CANOPIES

Activity Type Production Rate Equipment Team Size Notes
Main Structure Steel 15-20m/day Mobile crane 10-12 Including columns
Roof Panels Glazed/Metal 100-120m²/day Mobile lift 8-10 Including sealing
Drainage Integral 30-40m/day Mobile lift 6-8 Including downpipes
Lighting Integration 25-30m/day Mobile lift 6-8 Including wiring

ENTRANCE PROTECTION

Activity Type Production Rate Equipment Team Size Notes
Wind Screens Glass 20-25m²/day Mobile crane 8-10 Including frames
Rain Shelters Covered 15-20m/day Mobile crane 8-10 Including drainage
Heat Barriers Thermal 25-30m/day Mobile lift 6-8 Including sensors
Door Systems Automatic 2-3 sets/day Manual 6-8 Including controls
  1. STATION BICYCLE FACILITIES (DETAILED)

SECURE STORAGE

Activity Type Production Rate Equipment Team Size Notes
Bike Racks Standard 15-20 units/day Manual 6-8 Including anchoring
Secure Lockers Individual 8-10 units/day Mobile lift 6-8 Including locks
CCTV Coverage Security 6-8 cameras/day Mobile lift 4-6 Including testing
Access Control Electronic 4-5 units/day Manual 4-6 Including programming

SUPPORT FACILITIES

Activity Type Production Rate Equipment Team Size Notes
Repair Stations Self-service 2-3 units/day Manual 4-6 Including tools
Pump Stations Air supply 3-4 units/day Manual 4-6 Including plumbing
Information Digital/Static 5-6 units/day Manual 4-6 Including updates
Lighting Security 8-10 units/day Mobile lift 6-8 Including sensors
  1. STATION TAXI/RIDESHARE FACILITIES (DETAILED)

QUEUE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Barrier Rails Stainless 40-50m/day Manual 6-8 Including fixings
Digital Displays Information 4-5 units/day Mobile lift 6-8 Including power
Call Points Service 3-4 units/day Manual 4-6 Including comms
Weather Protection Shelters 2-3 units/day Mobile crane 8-10 Including drainage

MANAGEMENT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Control Room Equipment 1 room/2 days Manual 6-8 Including furniture
CCTV Coverage Security 6-8 cameras/day Mobile lift 4-6 Including network
Information System Digital 1 system/day Manual 4-6 Including setup
Payment Kiosks Automated 2-3 units/day Manual 4-6 Including testing

 

  1. STATION ACCESSIBILITY SYSTEMS (DETAILED)

TACTILE GUIDANCE

Activity Type Production Rate Equipment Team Size Notes
Warning Strips Platform edge 60-80m/day Manual 6-8 Including adhesive
Directional Path Navigation 50-70m/day Manual 6-8 Including setting out
Braille Signs Information 15-20 units/day Manual 4-6 Including mounting
Floor Markers Decision points 25-30 units/day Manual 4-6 Including inlays

AUDIO-VISUAL AIDS

Activity Type Production Rate Equipment Team Size Notes
Hearing Loops Counter/Area 4-5 units/day Manual 4-6 Including testing
Audio Beacons Navigation 8-10 units/day Mobile lift 4-6 Including setup
Visual Displays High contrast 6-8 units/day Mobile lift 6-8 Including calibration
Voice Guidance Systems 1 system/day Manual 4-6 Including programming
  1. STATION CUSTOMER SERVICE FACILITIES (DETAILED)

SERVICE COUNTERS

Activity Type Production Rate Equipment Team Size Notes
Main Counter Full service 1 unit/2 days Manual 8-10 Including services
Quick Service Simple 2-3 units/day Manual 6-8 Including equipment
Security Glass Protected 15-20m²/day Mobile lift 6-8 Including frames
Queue Systems Electronic 1 system/day Manual 4-6 Including displays

STAFF FACILITIES

Activity Type Production Rate Equipment Team Size Notes
Back Office Workspace 1 room/3 days Manual 8-10 Including furniture
Storage Areas Secure 1 room/2 days Manual 6-8 Including shelving
Break Room Staff 1 room/3 days Manual 6-8 Including amenities
Locker Room Personal 20-25 lockers/day Manual 4-6 Including benches
  1. STATION FIRST AID FACILITIES (DETAILED)

TREATMENT ROOMS

Activity Type Production Rate Equipment Team Size Notes
Main Room Medical 1 room/3 days Manual 8-10 Including services
Equipment Install Medical 1 room/day Manual 4-6 Including testing
Storage Units Secure 4-5 units/day Manual 4-6 Including assembly
Hand Wash Clinical 2-3 units/day Manual 4-6 Including plumbing

EMERGENCY EQUIPMENT

Activity Type Production Rate Equipment Team Size Notes
AED Units Defibrillator 4-5 units/day Manual 4-6 Including cabinets
First Aid Kits Wall mounted 8-10 units/day Manual 4-6 Including signage
Emergency Call Points 6-8 units/day Manual 4-6 Including testing
Stretcher Store Equipment 2-3 units/day Manual 4-6 Including access
  1. STATION LOST PROPERTY (DETAILED)

STORAGE SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Secure Storage Shelving 15-20 units/day Manual 6-8 Including assembly
Valuable Safe High security 1-2 units/day Manual 4-6 Including anchoring
Tracking System Digital 1 system/day Manual 4-6 Including setup
Collection Point Counter 1 unit/day Manual 6-8 Including security

MANAGEMENT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Database Software 1 system/day Manual 2-4 Including training
Label Printers Equipment 3-4 units/day Manual 2-4 Including network
Search System Digital 1 system/day Manual 2-4 Including setup
CCTV Coverage Security 4-5 cameras/day Manual 4-6 Including testing

 

  1. STATION STAFF FACILITIES (DETAILED)

LOCKER ROOMS

Activity Type Production Rate Equipment Team Size Notes
Lockers Personal 25-30 units/day Manual 6-8 Including numbering
Changing Areas Private 1 area/2 days Manual 8-10 Including benches
Shower Units Individual 3-4 units/day Manual 6-8 Including plumbing
Drying Room Ventilated 1 room/2 days Manual 6-8 Including equipment

BREAK FACILITIES

Activity Type Production Rate Equipment Team Size Notes
Kitchen Area Staff 1 room/3 days Manual 8-10 Including appliances
Rest Area Furnished 1 room/2 days Manual 6-8 Including furniture
Quiet Room Private 1 room/2 days Manual 4-6 Including soundproofing
Meeting Space Multi-use 1 room/3 days Manual 6-8 Including AV equipment
  1. STATION CONTROL ROOM (DETAILED)

OPERATIONS CENTER

Activity Type Production Rate Equipment Team Size Notes
Console Install Operator 2-3 units/day Manual 8-10 Including ergonomics
Display Wall Video 1 wall/3 days Mobile lift 10-12 Including calibration
Equipment Racks Technical 3-4 units/day Manual 6-8 Including cabling
HVAC Systems Precision 1 system/2 days Various 8-10 Including controls

SUPPORT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
UPS Install Backup 1 system/2 days Forklift 8-10 Including testing
Fire Suppress Gas 1 system/3 days Various 8-10 Including sensors
Access Control Security 1 system/day Manual 4-6 Including biometrics
Emergency Comm Systems 1 system/2 days Manual 6-8 Including redundancy
  1. STATION MAINTENANCE FACILITIES (DETAILED)

WORKSHOP AREAS

Activity Type Production Rate Equipment Team Size Notes
Workbenches Heavy duty 4-5 units/day Manual 6-8 Including services
Tool Storage Secure 3-4 units/day Manual 4-6 Including organization
Testing Area Equipment 1 area/2 days Various 6-8 Including power
Spare Parts Storage 10-12 units/day Manual 4-6 Including shelving

EQUIPMENT ROOMS

Activity Type Production Rate Equipment Team Size Notes
Plant Room Access 1 room/3 days Various 8-10 Including platforms
Service Lifts Material 1 unit/4 days Mobile crane 10-12 Including testing
Loading Bay Delivery 1 bay/2 days Various 8-10 Including dock leveler
Waste Area Segregated 1 area/2 days Manual 6-8 Including containment
  1. STATION BACKUP SYSTEMS (DETAILED)

POWER SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Generators Emergency 1 unit/3 days Heavy crane 10-12 Including fuel system
UPS Units Critical 2-3 units/day Forklift 8-10 Including batteries
Transfer Switch Automatic 1-2 units/day Manual 6-8 Including controls
Distribution Emergency 1 system/2 days Manual 8-10 Including testing

COMMUNICATION BACKUP

Activity Type Production Rate Equipment Team Size Notes
Radio System Redundant 1 system/2 days Manual 6-8 Including antennas
Data Backup Servers 2-3 units/day Manual 4-6 Including configuration
Emergency Phone Direct line 4-5 units/day Manual 4-6 Including testing
Satellite Link Backup 1 system/2 days Various 6-8 Including alignment

 

  1. STATION WATER MANAGEMENT SYSTEMS (DETAILED)

POTABLE WATER

Activity Type Production Rate Equipment Team Size Notes
Main Supply Distribution 40-50m/day Excavator 8-10 Including testing
Storage Tanks Domestic 1-2 units/day Mobile crane 8-10 Including connections
Booster Pumps Pressure 2-3 sets/day Manual 6-8 Including controls
Monitoring Quality 1 system/day Manual 4-6 Including sensors

GREY WATER

Activity Type Production Rate Equipment Team Size Notes
Collection System 30-40m/day Excavator 8-10 Including tanks
Treatment Plant 1 unit/3 days Mobile crane 10-12 Including setup
Distribution Recycled 35-45m/day Manual 6-8 Including marking
Control System Automated 1 system/day Manual 4-6 Including programming
  1. STATION ENERGY MANAGEMENT (DETAILED)

MONITORING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Power Meters Smart 8-10 units/day Manual 4-6 Including network
Sub-metering Distribution 6-8 units/day Manual 4-6 Including setup
Data Loggers Energy 10-12 units/day Manual 4-6 Including calibration
Analytics Software 1 system/day Manual 2-4 Including training

EFFICIENCY MEASURES

Activity Type Production Rate Equipment Team Size Notes
LED Upgrade Lighting 40-50 units/day Mobile lift 6-8 Including controls
Motion Sensors Presence 15-20 units/day Manual 4-6 Including setup
Solar Panels Renewable 20-25 panels/day Mobile crane 8-10 Including mounting
Heat Recovery System 1 system/3 days Various 8-10 Including ducting
  1. STATION PEST CONTROL SYSTEMS (DETAILED)

PREVENTION SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Barriers Physical 50-60m/day Manual 6-8 Including sealing
Sonic Devices Electronic 8-10 units/day Manual 4-6 Including power
UV Traps Insect 6-8 units/day Mobile lift 4-6 Including electrical
Bait Stations Secure 15-20 units/day Manual 4-6 Including monitoring

MONITORING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
CCTV Coverage Detection 6-8 cameras/day Mobile lift 6-8 Including setup
Motion Sensors Activity 10-12 units/day Manual 4-6 Including calibration
Data Collection Units 4-5 units/day Manual 2-4 Including network
Reporting Software 1 system/day Manual 2-4 Including training
  1. STATION AIR QUALITY MONITORING (DETAILED)

SENSOR NETWORKS

Activity Type Production Rate Equipment Team Size Notes
PM Sensors Particulate 8-10 units/day Mobile lift 4-6 Including calibration
CO2 Monitors Level 10-12 units/day Manual 4-6 Including setup
VOC Detectors Chemical 6-8 units/day Manual 4-6 Including testing
Temperature Climate 12-15 units/day Manual 4-6 Including network

CONTROL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Central Unit Processing 1 unit/day Manual 6-8 Including programming
Display Panels Information 4-5 units/day Mobile lift 6-8 Including power
Ventilation Control 1 system/2 days Manual 6-8 Including integration
Data Analysis Software 1 system/day Manual 2-4 Including setup

 

  1. STATION NOISE CONTROL SYSTEMS (DETAILED)

ACOUSTIC TREATMENTS

Activity Type Production Rate Equipment Team Size Notes
Wall Panels Absorptive 50-60m²/day Mobile lift 6-8 Including mounting
Ceiling Baffles Suspended 40-50m²/day Mobile lift 6-8 Including fixings
Platform Screens Barrier 20-25m/day Mobile crane 8-10 Including foundations
Door Seals Acoustic 15-20 units/day Manual 4-6 Including adjustment

MONITORING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Sound Meters Fixed 6-8 units/day Manual 4-6 Including calibration
Data Loggers Recording 4-5 units/day Manual 4-6 Including setup
Warning Display Visual 3-4 units/day Mobile lift 6-8 Including power
Analysis System Software 1 system/day Manual 2-4 Including configuration
  1. STATION WEATHER MONITORING (DETAILED)

SENSOR SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Weather Station Complete 1-2 units/day Mobile crane 8-10 Including mounting
Wind Sensors Anemometer 4-5 units/day Mobile lift 6-8 Including calibration
Rain Gauges Digital 6-8 units/day Manual 4-6 Including setup
Temperature Probes 10-12 units/day Manual 4-6 Including testing

INTEGRATION SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Control Unit Central 1 unit/day Manual 6-8 Including programming
Display Boards Information 2-3 units/day Mobile lift 6-8 Including network
Alert System Warning 1 system/day Manual 4-6 Including setup
Data Storage Cloud 1 system/day Manual 2-4 Including testing
  1. STATION ASSET TRACKING (DETAILED)

RFID SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Tag Install Equipment 100-120 units/day Manual 4-6 Including programming
Readers Fixed 8-10 units/day Manual 4-6 Including mounting
Portals Gateway 2-3 units/day Mobile lift 6-8 Including power
Handheld Units Mobile 5-6 units/day Manual 2-4 Including setup

MANAGEMENT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Database Setup 1 system/day Manual 4-6 Including population
Asset Register Digital 200-250 items/day Manual 4-6 Including verification
Maintenance Planning 1 system/day Manual 4-6 Including scheduling
Reporting Tools 1 system/day Manual 2-4 Including training
  1. STATION QUEUE MONITORING (DETAILED)

DETECTION SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Cameras Analytics 6-8 units/day Mobile lift 6-8 Including setup
Sensors Presence 10-12 units/day Manual 4-6 Including calibration
Counters Automatic 8-10 units/day Manual 4-6 Including testing
Displays Information 4-5 units/day Mobile lift 6-8 Including network

MANAGEMENT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Control Room Equipment 1 room/2 days Manual 8-10 Including furniture
Software Analytics 1 system/day Manual 4-6 Including setup
Staff Alerts Mobile 1 system/day Manual 4-6 Including testing
Historical Data Storage 1 system/day Manual 2-4 Including configuration
  1. STATION CROWD MANAGEMENT SYSTEMS (DETAILED)

FLOW CONTROL

Activity Type Production Rate Equipment Team Size Notes
Gates Automated 3-4 units/day Mobile crane 8-10 Including controls
Barriers Retractable 15-20 units/day Manual 6-8 Including mounting
Direction Signs LED 8-10 units/day Mobile lift 6-8 Including power
Emergency Exit Push bars 6-8 units/day Manual 4-6 Including testing

MONITORING SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Density Sensors Overhead 6-8 units/day Mobile lift 6-8 Including calibration
AI Cameras Analytics 4-6 units/day Mobile lift 6-8 Including setup
Control Software Integration 1 system/day Manual 4-6 Including programming
Alert Systems Emergency 1 system/day Manual 4-6 Including testing
  1. STATION PLATFORM EDGE PROTECTION (DETAILED)

SAFETY SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Warning Strip Tactile 50-60m/day Manual 8-10 Including adhesive
Edge Lighting LED 40-50m/day Manual 6-8 Including wiring
Safety Barriers Fixed 30-35m/day Mobile crane 8-10 Including anchoring
Emergency Stop Buttons 15-20 units/day Manual 4-6 Including testing

MONITORING EQUIPMENT

Activity Type Production Rate Equipment Team Size Notes
CCTV Coverage Platform 6-8 units/day Mobile lift 6-8 Including setup
Intrusion Detection Sensors 20-25 units/day Manual 4-6 Including calibration
Warning Systems Audio/Visual 10-12 units/day Mobile lift 6-8 Including testing
Control Interface Integration 1 system/day Manual 4-6 Including programming
  1. STATION ESCALATOR MONITORING (DETAILED)

SENSOR SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Speed Sensors Digital 4-5 units/day Manual 4-6 Including calibration
Load Monitors Weight 3-4 units/day Manual 4-6 Including setup
Temperature Bearings 6-8 units/day Manual 4-6 Including testing
Vibration Analysis 4-5 units/day Manual 4-6 Including mounting

CONTROL INTEGRATION

Activity Type Production Rate Equipment Team Size Notes
Control Panel Main 1 unit/day Manual 6-8 Including programming
Data Collection System 1 system/day Manual 4-6 Including setup
Remote Access Network 1 system/day Manual 4-6 Including security
Maintenance Alert Software 1 system/day Manual 2-4 Including training
  1. STATION LIFT MONITORING (DETAILED)

OPERATIONAL SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Performance Monitor Digital 2-3 units/day Manual 4-6 Including setup
Door Sensors Safety 6-8 units/day Manual 4-6 Including calibration
Load Cells Weight 4-5 units/day Manual 4-6 Including testing
Emergency Comms Two-way 3-4 units/day Manual 4-6 Including testing

MANAGEMENT SYSTEMS

Activity Type Production Rate Equipment Team Size Notes
Control Room Equipment 1 room/2 days Manual 6-8 Including furniture
Data Analysis Software 1 system/day Manual 4-6 Including setup
Remote Control Access 1 system/day Manual 4-6 Including security
Maintenance Log Digital 1 system/day Manual 2-4 Including training

 

 


Other production rates – Indicative only

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO