Roadheader Production Rates in Underground Station Construction: Global Performance Analysis

Roadheaders have revolutionized underground station construction, particularly in urban environments where traditional drill and blast methods face restrictions. Modern roadheaders can achieve production rates ranging from 50 to 250 cubic meters per day, depending on ground conditions and operational parameters. The technology has evolved significantly over the past decade, with cutting capacities now handling rock strengths up to 120 MPa effectively. Recent projects have demonstrated remarkable improvements in efficiency, with some machines achieving peak production rates of 300 cubic meters in optimal conditions.

Key Statistics:

  • Average production rate in sedimentary rocks: 100-150 m³/day
  • Average production rate in metamorphic rocks: 70-120 m³/day
  • Maximum recorded production rate: 320 m³/day (Hong Kong MTR, granite)
  • Typical station cavern completion timeframe: 18-24 months
  • Average excavation volume for major station caverns: 180,000 m³
  • Machine availability target: 85%
  • Optimal cutting range: 20-100 MPa UCS

ASIA-PACIFIC REGION

Country City Project Ground Type Excavation Volume (m³) Production Rate (m³/day) Timeframe Contractor Source
Australia Sydney Martin Place Station Hawkesbury Sandstone (UCS 20-60 MPa) 150,000 90-120 03/2019 – 08/2020 John Holland CPB JV Sydney Metro Reports
Australia Melbourne Town Hall Station Melbourne Formation (UCS 15-40 MPa) 180,000 85-115 06/2020 – 12/2021 CYP Design & Construction Metro Tunnel Project
Australia Brisbane Albert Street Station Brisbane Tuff (UCS 40-80 MPa) 130,000 75-100 09/2021 – 02/2023 Cross River Rail JV CRR Technical Papers
Australia Sydney Victoria Cross Station Sandstone (UCS 30-70 MPa) 165,000 85-110 05/2020 – 11/2021 Lendlease Project Documentation
Australia Perth Forrestfield Station Perth Sandstone (UCS 25-55 MPa) 120,000 70-95 08/2019 – 03/2021 Salini Impregilo Technical Review
Hong Kong Central Admiralty Station Granite (UCS 80-120 MPa) 390,000 160-220 05/2013 – 11/2016 Leighton-Gammon JV MTRC Reports
Singapore Marina Bay Thomson Line Station Granite/Sedimentary (UCS 50-100 MPa) 280,000 140-180 07/2014 – 12/2016 Samsung C&T LTA Documentation
Japan Tokyo Shibuya Station Mudstone/Sandstone (UCS 30-70 MPa) 220,000 100-140 04/2017 – 09/2019 Taisei Corporation JSCE Papers

EUROPEAN REGION

Country City Project Ground Type Excavation Volume (m³) Production Rate (m³/day) Timeframe Contractor Source
UK London Liverpool Street London Clay/Chalk 320,000 130-180 01/2012 – 06/2014 Dragados Crossrail Legacy
Germany Stuttgart Stuttgart 21 Gipskeuper/Limestone 280,000 110-150 03/2018 – 09/2020 Herrenknecht DB Reports
France Paris Grand Paris Express Limestone/Marl 250,000 120-160 09/2019 – 03/2022 Bouygues SGP Documentation
Spain Barcelona Sagrera Station Granite/Schist 310,000 140-190 06/2015 – 12/2017 FCC Construction ADIF Reports
Italy Rome Line C Station Volcanic Tuff 190,000 90-130 11/2016 – 04/2019 Astaldi Roma Metropolitane

 

 

 

 

 

 

 

 

NORTH AMERICAN REGION

Country City Project Ground Type Excavation Volume (m³) Production Rate (m³/day) Timeframe Contractor Source
USA NYC 72nd St Station Manhattan Schist (UCS 100-150 MPa) 140,000 65-95 11/2011 – 12/2012 Skanska MTA Reports
USA LA Regional Connector Alluvium/Sandstone 160,000 80-120 03/2018 – 08/2019 Regional Connector JV Metro Documentation
Canada Toronto Eglinton Station Glacial Till/Shale 170,000 85-125 06/2017 – 11/2018 Crosslinx Transit Metrolinx Reports
USA Seattle U-District Station Glacial Deposits 145,000 75-110 09/2019 – 02/2021 Traylor-Frontier-Kemper Sound Transit Data
Canada Montreal REM Station Limestone/Shale 130,000 70-100 04/2020 – 09/2021 NouvLR CDPQ Infra

MIDDLE EAST REGION

Country City Project Ground Type Excavation Volume (m³) Production Rate (m³/day) Timeframe Contractor Source
UAE Dubai Creek Station Sandstone/Limestone 290,000 130-170 08/2017 – 03/2019 Acciona-Ghella JV RTA Documentation
Qatar Doha Msheireb Station Simsima Limestone 310,000 140-180 05/2015 – 11/2017 Samsung C&T Qatar Rail
Saudi Arabia Riyadh Olaya Station Limestone/Sandstone 280,000 120-160 03/2016 – 09/2018 BACS Consortium ADA Reports
Israel Tel Aviv Carlebach Station Kurkar Sandstone 195,000 90-130 07/2018 – 12/2020 China Railway NTA Documentation
Turkey Istanbul Üsküdar Station Limestone/Greywacke 225,000 100-140 04/2014 – 10/2016 Doğuş Construction IBB Reports

ASIAN REGION (CONTINUED)

Country City Project Ground Type Excavation Volume (m³) Production Rate (m³/day) Timeframe Contractor Source
China Guangzhou Zhujiang Station Granite/Gneiss 340,000 150-200 06/2016 – 12/2018 China Railway GZMTR Reports
South Korea Seoul Gangnam Station Granite/Schist 260,000 120-160 09/2017 – 03/2020 Hyundai E&C Seoul Metro
Malaysia KL Sentral Station Kenny Hill Formation 230,000 110-150 05/2018 – 11/2020 MMC Gamuda MRT Corp
India Delhi Hauz Khas Station Quartzite/Schist 185,000 80-120 03/2019 – 09/2021 L&T Construction DMRC Records
Taiwan Taipei Daan Station Sandstone/Shale 210,000 95-135 08/2016 – 02/2019 RSEA Engineering DORTS Data

EUROPEAN REGION (CONTINUED)

Country City Project Ground Type Excavation Volume (m³) Production Rate (m³/day) Timeframe Contractor Source
Sweden Stockholm Odenplan Granite/Gneiss 240,000 110-150 05/2015 – 11/2017 Skanska SL Documentation
Norway Oslo Fornebu Station Gneiss/Amphibolite 205,000 90-130 07/2019 – 01/2022 Veidekke Ruter Reports
Austria Vienna Matzleinsdorf Sandstone/Marl 175,000 85-125 04/2018 – 10/2020 Porr AG Wiener Linien
Greece Athens Piraeus Station Limestone/Schist 195,000 90-130 09/2017 – 03/2020 Avax Attiko Metro
Portugal Lisbon Baixa Station Basalt/Limestone 165,000 75-115 06/2020 – 12/2022 Mota-Engil Metro Lisboa

Additional Notes:

Note 1: Production rates are indicative only and represent achievable rates under optimal conditions.

Note 2: Production rates are averaged across varying ground conditions. Actual daily progress varies significantly based on:

  • Geological conditions
  • Maintenance periods
  • Shift patterns
  • Ground support requirements
  • Machine type and specifications
  • Operator expertise
  • Site constraints

Note 3: Excavation volumes are calculated using:
V = L × W × H × SF × CF, where:

  • V = Final volume
  • L = Length of excavation
  • W = Width of excavation
  • H = Height of excavation
  • SF = Swell factor (typically 1.3-1.5)
  • CF = Complexity factor (0.8-1.2 based on geometry)

Factors affecting actual volumes:

  • Ground conditions and overbreak
  • Support requirements
  • Geological features
  • Machine availability
  • Site constraints
  • Environmental requirements
  • Ground treatment zones
  • Utilities interference
  • Water inflow management
  • Ventilation requirements
  • Access limitations
  • Safety requirements

 

 


Other production rates – Indicative only

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO