Slab Track Construction in Railway Stations: Global Production Analysis

Slab track construction in railway stations represents a critical component of modern rail infrastructure, offering superior stability, reduced maintenance, and longer service life compared to traditional ballasted track. Production rates vary significantly based on construction methodology, station configuration, and site constraints. Recent technological advances, including automated concrete placing systems and prefabricated elements, have improved installation efficiency. The choice between in-situ and precast systems significantly influences production rates, with some projects achieving installation rates of up to 50 meters per day in optimal conditions.

Key Statistics:

  • Average production rate (in-situ): 20-30m/day
  • Precast system installation: 30-40m/day
  • Concrete pour volumes: 40-60m³/day
  • Rail fastening installation: 40-50m/day
  • Typical accuracy: +/- 2mm
  • Best practice completion: 200m/week
  • Average station platform length: 250m
  • Typical curing time: 7-14 days

AUSTRALIA REGION

Country City Project System Type Length (m) Method Production Rate (m/day) Duration (months) Timeframe Contractor Source
Australia Sydney Central Station Rheda 2000 750 In-situ 25-30 8 2021-2022 Laing O’Rourke Sydney Metro
Australia Melbourne Metro Tunnel ÖBB-Porr 550 Precast 35-40 6 2020-2021 CYP JV MTIA Data
Australia Brisbane Cross River LVT System 620 In-situ 20-25 7 2022-2023 CPB-BAM CRR Reports
Australia Perth Airport Link Rheda City 480 In-situ 22-28 5 2019-2020 Salini-NRW PTA Records
Australia Sydney Martin Place Züblin 680 Precast 30-35 6 2021-2022 John Holland TfNSW Data

EUROPEAN REGION

Country City Project System Type Length (m) Method Production Rate (m/day) Duration (months) Timeframe Contractor Source
Germany Stuttgart S21 Station Bögl 820 Precast 35-45 7 2020-2021 Hochtief DB Reports
UK London Liverpool St LVT System 750 In-situ 25-30 8 2019-2020 Costain Crossrail
France Paris Line 15 Sateba 680 Precast 30-40 6 2021-2022 Vinci RATP Data
Spain Barcelona Sagrera Edilon 580 In-situ 20-25 7 2020-2021 FCC ADIF Docs
Italy Rome Metro C FF Bögl 450 Precast 32-38 5 2021-2022 Astaldi Roma Metro

ASIAN REGION

Country City Project System Type Length (m) Method Production Rate (m/day) Duration (months) Timeframe Contractor Source
China Shanghai Hongqiao CRTS III 960 Precast 40-50 8 2020-2021 CRCC CRH Data
Japan Tokyo Shibuya J-Slab 680 Precast 35-45 6 2019-2020 JR East JRTT Reports
Singapore Woodlands TEL Rheda 2000 550 In-situ 25-30 7 2021-2022 Samsung C&T LTA Records
Hong Kong Central Admiralty Shinkansen 720 Precast 30-40 8 2020-2021 Gammon MTR Data
Korea Seoul GTX Line KR Type 840 Precast 35-45 7 2021-2022 Hyundai KRNA Docs

System-Specific Production Rates:

Precast Systems:

  1. Bögl System:
  • Panel installation: 40-50m/day
  • Grouting: 35-45m/day
  • Rail fastening: 45-55m/day
  • Final alignment: 30-40m/day
  1. Shinkansen Type:
  • Base preparation: 45-55m/day
  • Panel placement: 35-45m/day
  • Joint sealing: 40-50m/day
  • Rail installation: 35-45m/day

In-situ Systems:

  1. Rheda 2000:
  • Base slab: 25-30m/day
  • Rail positioning: 30-35m/day
  • Concrete pour: 20-25m/day
  • Finishing: 15-20m/day
  1. LVT System:
  • Boot installation: 35-40m/day
  • Rail setup: 30-35m/day
  • Concrete pour: 25-30m/day
  • Curing time: 7 days

Quality Control Metrics:

  1. Geometric Tolerances:
  • Horizontal: ±2mm
  • Vertical: ±1mm
  • Gauge: ±1mm
  • Twist: 1mm/3m
  1. Material Requirements:
  • Concrete strength: 40-60 MPa
  • Rail hardness: 260-320 HB
  • Elastomer shore: 60-70
  • Electrical resistance: >5kΩ

Installation Equipment:

  1. Precast Systems:
  • Gantry crane capacity: 20-30t
  • Vacuum lifters
  • Laser guidance systems
  • Auto-leveling equipment
  1. In-situ Systems:
  • Rail positioning frames
  • Concrete pumps
  • Power screeds
  • Survey equipment

 

Production Rate Analysis by System Type:

In-situ Systems:

  1. Base Slab Installation:
  • Preparation: 30-35m/day
  • Reinforcement: 25-30m/day
  • Concrete placing: 20-25m/day
  • Finishing: 15-20m/day
  1. Rail Installation:
  • Setting out: 40-50m/day
  • Rail positioning: 35-40m/day
  • Final adjustment: 30-35m/day
  1. Quality Control:
  • Survey checks: 100m/day
  • Rail geometry: 80m/day
  • Documentation: 150m/day

 

Note 1: Production rates are indicative only.

Note 2: Rates vary based on:

  • Station configuration
  • Access constraints
  • Interface with other works
  • Concrete supply chain
  • Weather conditions
  • Resource availability

Note 3: Progress calculation formula:
P = (L × S × E) / T, where:

  • P = Production rate
  • L = Length completed
  • S = System factor (0.8-1.2)
  • E = Efficiency factor (0.7-0.9)
  • T = Time period

Influencing Factors:

  • Platform interface
  • Services coordination
  • Material logistics
  • Quality requirements
  • Safety constraints
  • Environmental controls
  • Testing regime
  • Stakeholder requirements

 

 


Other production rates – Indicative only

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock