Stabling yard construction involves complex track layouts, signaling systems, and maintenance facilities requiring precise staging and coordination. Production rates vary significantly based on yard configuration, ground conditions, and interface requirements. Modern construction methods including automated track laying and prefabricated turnouts have improved delivery timeframes, with some projects achieving track installation rates of up to 200m per day under optimal conditions.
Key Statistics:
- Average yard capacity: 15-30 trains
- Typical track length: 5-15km total
- Track installation: 150-200m/day
- Turnout installation: 1-2 units/week
- OHW installation: 200-300m/day
- Typical project duration: 18-24 months
- Best practice completion: 15 months
- Average cost: $80-150M
AUSTRALIA REGION
| Location | Project | Scope | Track (km) | Elements | Duration (months) | Start-End | Production Rate | Contractor | Cost ($M) | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Sydney | Mortdale | 20 Cars | 8.5 | T,S,OHW,B | 22 | Mar20-Jan22 | 180m track/day | John Holland | 125 | TfNSW |
| Melbourne | Pakenham East | 30 Cars | 12.4 | T,S,OHW,B,M | 24 | Jun19-Jun21 | 160m track/day | CPB | 168 | MTIA |
| Brisbane | Mayne | 15 Cars | 6.8 | T,S,OHW,B | 18 | Sep20-Mar22 | 150m track/day | Laing O’Rourke | 95 | QR |
| Perth | Bellevue | 25 Cars | 10.2 | T,S,OHW,B,M | 20 | Apr21-Dec22 | 170m track/day | Downer EDI | 145 | PTA |
| Sydney | Tallawong | 22 Cars | 9.6 | T,S,OHW,B | 21 | Jul20-Apr22 | 175m track/day | CPB/UGL | 132 | Metro |
Key:
T = Track
S = Signaling
OHW = Overhead Wiring
B = Buildings
M = Maintenance Facilities
Production Rate Analysis by Element:
Track Installation:
- Mainline Track:
- Formation: 300-400m/day
- Track laying: 150-200m/day
- Ballasting: 250-300m/day
- Tamping: 400-500m/day
- Turnouts:
- Assembly: 3-4 days/unit
- Installation: 2-3 days/unit
- Commissioning: 1-2 days/unit
- OHW Installation:
- Mast foundation: 8-10/day
- Mast erection: 12-15/day
- Wire running: 250-300m/day
- Registration: 200-250m/day
Buildings and Facilities:
- Maintenance Sheds:
- Foundation: 4-6 weeks
- Structure: 8-10 weeks
- Fit-out: 12-14 weeks
- Staff Facilities:
- Foundation: 3-4 weeks
- Structure: 6-8 weeks
- Fit-out: 8-10 weeks
Signaling Installation:
- Equipment Rooms:
- Construction: 12-16 weeks
- Equipment install: 8-10 weeks
- Testing: 6-8 weeks
- Field Equipment:
- Cable routes: 200-250m/day
- Signal installation: 2-3/day
- Points machines: 1-2/day
Project Phases:
Site Preparation:
- Clearing: 5,000-7,000m²/week
- Bulk earthworks: 2,000-3,000m³/day
- Drainage: 50-70m/day
- Services: 80-100m/day
Track Infrastructure:
- Formation: 250-300m/day
- Track slab/ballast: 200-250m/day
- Rail installation: 150-200m/day
- Welding/stressing: 100-150m/day
Systems Installation:
- Power supply: 150-200m/day
- Signaling: 100-150m/day
- Communications: 200-250m/day
- Security systems: 300-400m/day
Would you like additional details on specific aspects or more examples?
Note 1: Production rates are indicative only.
Note 2: Rates vary based on:
- Site conditions
- Access constraints
- Interface requirements
- Resource availability
- Weather impacts
- Staging requirements
Note 3: Duration calculation formula:
D = (BQ × CF × IF) + TC, where:
- D = Total duration
- BQ = Base quantity duration
- CF = Complexity factor (1.0-1.8)
- IF = Interface factor (1.0-1.5)
- TC = Testing/commissioning constant
Influencing Factors:
- Ground conditions
- Environmental constraints
- Operational interfaces
- Utility conflicts
- Material supply
- Labor availability
- Weather impacts
- Approval processes
- Testing requirements
- Integration with existing systems
Other production rates – Indicative only
- RAIL INDUSTRY PRODUCTION RATES COMPREHENSIVE TABLE
-
- Ballast Cleaning Operations Analysis
- Canopy Installation Analysis for Aerial Concourses
- Cut and Fill Production Rates in Railway Station Construction
- CSR (Cable Service Routes) Installation Analysis
- Demolition Works Analysis for Railway Infrastructure
- Electrical Overlaps (OHW) 33kV Installation Analysis
- Elevated Service Access Platforms (ESAPs) for Stabling Yards Analysis
- Escalator Installation Analysis for Rail Stations
- Fence Installation Between Tracks Analysis (Live Corridor vs Possession Works)
- HDD Under Rail Tracks – 48-Hour Possession Analysis
- High-Speed Rail Construction Analysis
- Horizontal Directional Drilling (HDD)
- Lght Rail Construction Production Rates: Global Analysis
- Lift Replacement Projects Analysis
- Mechanical Gap Fillers Installation Analysis
- New Aerial Concourse Installation Analysis for Train Stations
- New Intercity Fleet (NIF) Platform Extension Projects Analysis
- Overhead Wire (OHW) Structure Installation Analysis
- Platform Extension Projects: Global Analysis
- Platform Marker Repainting Analysis
- Railway Sleeper Replacement Analysis
- Roadheader Production Rates in Underground Station Construction: Global Performance Analysis
- Screen Indicator Installation Analysis for Rail Stations
- Segregation Fence Installation Analysis Between Tracks
- Slab Track Construction in Railway Stations: Global Production Analysis
- Sound Barrier Installation Analysis Along Rail Corridors
- Stabling Yard Construction and Production Analysis
- Track Replacement in Railway Stations: Production Analysis
- Transport Access Program (TAP) Production Rates and Delivery Analysis
- Tunnel Boring Machine (TBM) Production Analysis and Performance Metrics
- Tunnel Membrane/Waterproofing Installation Analysis
- Under Line Crossing (ULX) Installation Analysis
- Underpass Access Construction Analysis for Train Stations
- Utilities Relocation in Railway Environments Analysis
- Water-Filled Traffic Barriers Installation Analysis