Transport Access Program projects focus on improving station accessibility through lifts, ramps, footbridges, and associated infrastructure. Production rates vary based on station complexity, existing infrastructure constraints, and construction staging requirements. Modern construction techniques, including prefabricated elements and modular construction, have significantly improved delivery timeframes, with some projects achieving lift installation in as little as 4-6 weeks under optimal conditions.
Key Statistics:
- Average lift installation: 8-12 weeks
- Footbridge installation: 4-8 weeks
- Typical project duration: 6-12 months
- Platform modifications: 100-150m²/week
- Canopy installation: 200-300m²/week
- Best practice completion: 6 months
- Average project cost: $15-25M
- Typical accessibility compliance rate: 95%
AUSTRALIA REGION
| Country | City | Station | Scope | Elements | Duration (months) | Start-End | Production Rate | Contractor | Cost ($M) | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Australia | Sydney | Wahroonga | 2 Lifts, FB | L2,FB1,C500 | 9 | Mar20-Dec20 | 8 weeks/lift | Haslin | 18 | TfNSW |
| Australia | NSW | Hawkesbury | 3 Lifts, Ramps | L3,R2,C600 | 12 | Jun19-Jun20 | 10 weeks/lift | Built | 22 | TAP Data |
| Australia | Sydney | Thornleigh | 2 Lifts, FB | L2,FB1,C400 | 8 | Sep20-May21 | 6 weeks/lift | Arenco | 15 | TAHE |
| Australia | NSW | Wyee | 2 Lifts, Ramps | L2,R3,C300 | 10 | Apr21-Feb22 | 9 weeks/lift | Downer | 16 | RAP Reports |
| Australia | Sydney | Yagoona | 3 Lifts, FB | L3,FB1,C700 | 11 | Jul20-Jun21 | 7 weeks/lift | Arenco | 20 | TfNSW Data |
AUSTRALIAN REGION (CONTINUED)
| Country | City | Station | Scope | Elements | Duration (months) | Start-End | Production Rate | Contractor | Cost ($M) | Source |
|---|---|---|---|---|---|---|---|---|---|---|
| Australia | NSW | Glenbrook | 2 Lifts, FB | L2,FB1,C400 | 8 | May21-Jan22 | 7 weeks/lift | Built | 17 | TfNSW |
| Australia | Sydney | Warwick Farm | 3 Lifts, Ramps | L3,R2,C800 | 11 | Aug20-Jul21 | 8 weeks/lift | Haslin | 21 | TAHE |
| Australia | NSW | Towradgi | 2 Lifts, FB | L2,FB1,C300 | 9 | Mar21-Dec21 | 6 weeks/lift | Arenco | 16 | RAP Data |
| Australia | Sydney | St Peters | 2 Lifts, Ramps | L2,R3,C500 | 10 | Jun20-Apr21 | 9 weeks/lift | Downer | 19 | TfNSW |
| Australia | NSW | Waitara | 3 Lifts, FB | L3,FB2,C600 | 12 | Sep20-Sep21 | 8 weeks/lift | Built | 23 | TAHE |
Element-Specific Production Rates:
Footbridges (FB):
- Prefabricated Steel:
- Foundation works: 3-4 weeks
- Assembly: 1-2 weeks
- Installation: 2-3 days
- Finishing: 2-3 weeks
- In-situ Concrete:
- Foundation works: 4-5 weeks
- Structure: 6-8 weeks
- Finishing: 3-4 weeks
Ramps and Stairs:
- Concrete Ramps:
- Foundation: 2-3 weeks
- Structure: 3-4 weeks
- Handrails: 1-2 weeks
- Steel Stairs:
- Foundation: 2 weeks
- Installation: 1-2 weeks
- Finishing: 1 week
Canopies (C):
- Modular System:
- Foundations: 2-3 weeks
- Structure: 1-2 weeks/100m²
- Roofing: 1 week/100m²
- Custom Design:
- Foundations: 3-4 weeks
- Structure: 2-3 weeks/100m²
- Roofing: 2 weeks/100m²
Project Delivery Timeframes:
Small Projects (<$15M):
- Design/Approval: 3-4 months
- Construction: 6-8 months
- Commissioning: 1-2 months
- Total: 10-14 months
Medium Projects ($15-25M):
- Design/Approval: 4-6 months
- Construction: 8-12 months
- Commissioning: 2-3 months
- Total: 14-18 months
Large Projects (>$25M):
- Design/Approval: 6-8 months
- Construction: 12-15 months
- Commissioning: 3-4 months
- Total: 18-24 months
Critical Success Factors:
- Planning Phase:
- Early stakeholder engagement
- Detailed site investigations
- Clear scope definition
- Realistic programming
- Risk assessment
- Resource planning
- Construction Phase:
- Efficient possession utilization
- Quality control
- Safety management
- Interface coordination
- Progress monitoring
- Change management
- Commissioning Phase:
- Systems integration
- Testing procedures
- Documentation
- Staff training
- Handover process
- Defect management
Key Performance Indicators:
- Time Management:
- Program compliance: 85-95%
- Possession delivery: 90-100%
- Milestone achievement: 80-90%
- Quality Metrics:
- DDA compliance: 100%
- Defect rates: <5%
- Customer satisfaction: >85%
- Safety Performance:
- Zero LTIs
- Safety observations: >10/week
- Toolbox talks: >2/week
Production Rate Analysis by Element:
Lift Installation:
- Standard Configuration:
- Shaft construction: 4-6 weeks
- Lift installation: 2-3 weeks
- Testing/commissioning: 2 weeks
- Complex Sites:
- Shaft construction: 6-8 weeks
- Lift installation: 3-4 weeks
- Testing/commissioning: 3 weeks
Note 1: Production rates are indicative only.
Note 2: Rates vary based on:
- Station complexity
- Heritage constraints
- Operating environment
- Access restrictions
- Service relocations
- Stakeholder requirements
Note 3: Duration calculation formula:
D = (BE × CF × IF) + CC, where:
- D = Total duration
- BE = Base element duration
- CF = Complexity factor (1.0-1.5)
- IF = Interface factor (1.0-1.3)
- CC = Commissioning constant
Influencing Factors:
- Heritage requirements
- Station operations
- Utility interfaces
- Weather impacts
- Material lead times
- Approval processes
- Community consultation
- Rail possessions availability
Note: Production rates assume:
- Normal working hours
- Standard access conditions
- Typical station configuration
- Average complexity
- Standard approval timeframes
- Regular possession availability
Additional Influencing Factors:
- Heritage requirements
- Environmental constraints
- Operational interfaces
- Community impacts
- Weather conditions
- Resource availability
- Material lead times
- Stakeholder requirements
Other production rates – Indicative only
- RAIL INDUSTRY PRODUCTION RATES COMPREHENSIVE TABLE
-
- Ballast Cleaning Operations Analysis
- Canopy Installation Analysis for Aerial Concourses
- Cut and Fill Production Rates in Railway Station Construction
- CSR (Cable Service Routes) Installation Analysis
- Demolition Works Analysis for Railway Infrastructure
- Electrical Overlaps (OHW) 33kV Installation Analysis
- Elevated Service Access Platforms (ESAPs) for Stabling Yards Analysis
- Escalator Installation Analysis for Rail Stations
- Fence Installation Between Tracks Analysis (Live Corridor vs Possession Works)
- HDD Under Rail Tracks – 48-Hour Possession Analysis
- High-Speed Rail Construction Analysis
- Horizontal Directional Drilling (HDD)
- Lght Rail Construction Production Rates: Global Analysis
- Lift Replacement Projects Analysis
- Mechanical Gap Fillers Installation Analysis
- New Aerial Concourse Installation Analysis for Train Stations
- New Intercity Fleet (NIF) Platform Extension Projects Analysis
- Overhead Wire (OHW) Structure Installation Analysis
- Platform Extension Projects: Global Analysis
- Platform Marker Repainting Analysis
- Railway Sleeper Replacement Analysis
- Roadheader Production Rates in Underground Station Construction: Global Performance Analysis
- Screen Indicator Installation Analysis for Rail Stations
- Segregation Fence Installation Analysis Between Tracks
- Slab Track Construction in Railway Stations: Global Production Analysis
- Sound Barrier Installation Analysis Along Rail Corridors
- Stabling Yard Construction and Production Analysis
- Track Replacement in Railway Stations: Production Analysis
- Transport Access Program (TAP) Production Rates and Delivery Analysis
- Tunnel Boring Machine (TBM) Production Analysis and Performance Metrics
- Tunnel Membrane/Waterproofing Installation Analysis
- Under Line Crossing (ULX) Installation Analysis
- Underpass Access Construction Analysis for Train Stations
- Utilities Relocation in Railway Environments Analysis
- Water-Filled Traffic Barriers Installation Analysis