Under Line Crossing (ULX) Installation Analysis

Under Line Crossing (ULX) installations require precise coordination of track possession, excavation, and service installation while maintaining track stability. Production rates vary significantly based on crossing width, depth, ground conditions, and installation methodology. Modern techniques including pipe jacking and horizontal directional drilling have improved efficiency, with some projects achieving installation rates of 3-4m per shift under optimal conditions.

Key Statistics:

  • Average production: 2-3m/shift
  • Typical depth: 1.8-2.5m
  • Crossing width: 6-15m
  • Crossing width per track: 4-5m
  • Additional width per track: 3.5-4m
  • Best practice completion: 1 crossing/weekend (2-3 tracks)
  • Excavation volume: 30-50mÂł/crossing/track
  • Jacking force: 50-200 tonnes
  • Jacking force increase per track: 40-60 tonnes
  • Installation accuracy: ±50mm
  • Track monitoring: 24/7
  • Track monitoring zones: 20m each side/trackAUSTRALIA REGION
Location Station Width (m) Method Duration (hrs) Rate (m/shift) Contractor Cost ($K) Source
Sydney Strathfield 12 Pipe Jack 48 2.5-3.0 John Holland 380 TfNSW
Melbourne Sunshine 9 Open Cut 72 1.5-2.0 CPB 420 MTM
Brisbane Northgate 8 HDD 36 2.0-2.5 Downer EDI 290 QR
Perth Bayswater 10 Pipe Jack 48 2.2-2.8 McConnell Dowell 350 PTA
Sydney Granville 15 Open Cut 72 1.8-2.2 Laing O’Rourke 460 Sydney Trains

Installation Method Analysis:

Pipe Jacking:

  1. Setup Phase:
  • Thrust pit: 8-10 hours
  • Reception pit: 6-8 hours
  • Track protection: 4-6 hours
  • Equipment setup: 4-5 hours
  1. Installation Phase:
  • Jacking rate: 0.5-1.0m/hour
  • Steering checks: Every 1m
  • Grouting: Continuous
  • Settlement monitoring: Hourly
  1. Completion Phase:
  • Service installation: 6-8 hours
  • Testing: 4-6 hours
  • Backfilling: 8-10 hours
  • Track reinstatement: 4-6 hours

Note 1: Production rates are indicative only.

Note 2: Rates vary based on:

  • Ground conditions
  • Water table
  • Track loading
  • Access constraints
  • Service requirements
  • Possession windows

Note 3: Volume calculation formula:
V = (π × D² × L × SF)/4, where:

  • V = Excavation volume
  • D = Pipe diameter
  • L = Crossing length
  • SF = Swell factor (1.3-1.5)

Influencing Factors:

  • Ground conditions
  • Track stability
  • Water ingress
  • Existing services
  • Access restrictions
  • Weather impacts
  • Material handling
  • Safety requirements

 

AUSTRALIA REGION

Location Station Width (m) Tracks Method Duration (hrs) Rate (m/shift) Contractor Cost ($K) Source
Sydney Strathfield 12 3 Pipe Jack 48 2.5-3.0 John Holland 380 TfNSW
Melbourne Sunshine 9 2 Open Cut 72 1.5-2.0 CPB 420 MTM
Brisbane Northgate 8 2 HDD 36 2.0-2.5 Downer EDI 290 QR
Perth Bayswater 14 4 Pipe Jack 56 2.2-2.8 McConnell Dowell 450 PTA
Sydney Granville 15 4 Open Cut 72 1.8-2.2 Laing O’Rourke 460 Sydney Trains

INTERNATIONAL REGION

Location Station Width (m) Tracks Method Duration (hrs) Rate (m/shift) Contractor Cost ($K) Source
UK-London Liverpool St 18 5 Pipe Jack 96 1.8-2.2 Balfour Beatty 580 Network Rail
Germany Frankfurt Hbf 16 4 HDD 72 2.2-2.6 Hochtief 520 DB
Japan Tokyo 20 6 Pipe Jack 108 1.5-2.0 Kajima 650 JR East
France Paris Nord 15 4 Open Cut 84 1.6-2.0 Vinci 490 SNCF
Hong Kong Kowloon 22 6 Pipe Jack 120 1.4-1.8 Gammon 680 MTR

Production Rate Analysis by Track Number:

2 Tracks:

  • Setup time: 8-10 hours
  • Installation: 1.5-2.0m/shift
  • Completion: 6-8 hours
  • Total duration: 36-48 hours

3 Tracks:

  • Setup time: 10-12 hours
  • Installation: 1.2-1.8m/shift
  • Completion: 8-10 hours
  • Total duration: 48-60 hours

4+ Tracks:

  • Setup time: 12-16 hours
  • Installation: 1.0-1.5m/shift
  • Completion: 10-14 hours
  • Total duration: 72-96 hours

Note 1: Production rates are indicative only.

Note 2: Rates vary based on:

  • Number of tracks
  • Track spacing
  • Track criticality
  • Service complexity
  • Ground conditions
  • Access constraints

Note 3: Volume calculation formula:
V = (π × D² × L × SF × TF)/4, where:

  • V = Excavation volume
  • D = Pipe diameter
  • L = Crossing length
  • SF = Swell factor (1.3-1.5)
  • TF = Track factor (1.0 per track)

Additional Considerations:

  • Track protection requirements increase with track numbers
  • Monitoring zones overlap with multiple tracks
  • Settlement tolerances more critical with multiple tracks
  • Possession planning complexity increases
  • Risk profile increases with track numbers
  • Equipment access more challenging
  • Material logistics more complex
  • Longer possession windows required

 


Other production rates – Indicative only

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO