For many railway employees, the Easter weekend represents an intense period of critical work. Over the past holiday weekend, the team successfully completed the “New Switch Connection Tomteboda” project by installing and commissioning two new switches between tracks D1 and U1 in Tomteboda (Karlberg).

Project Execution

  • Round-the-clock work commenced Thursday evening and continued through the weekend

  • Infrakraft’s portion of the work was completed late Sunday evening

  • Signaling system activation followed immediately after

  • Tracks returned to traffic control as planned by 06:00 Monday morning

Achievement Highlights

✔ Installation of two new switches in a high-traffic area
✔ Seamless coordination between construction and signaling teams
✔ On-time completion despite holiday working conditions

The project’s success was made possible by the dedicated efforts of all team members who worked through the holiday period. Special recognition goes to everyone involved for their professionalism and commitment.


More Info

 

 


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

By Possession Planning

Possession Planning is dedicated to providing news and insights for rail and road possession planning and delivery. Our mission is to serve as the premier information source for industry professionals managing critical infrastructure access, maintenance windows, and construction scheduling. Our Partners: FR2 Infrastructure | We Simplify Complexity | Construction Methodology | S | Energy Planning | Staging Diagrams . |

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading