The Wokingham Level Crossing renewal project demonstrates advanced infrastructure maintenance capabilities through complete track and crossing renewal within a critical 27-hour possession window. This Network Rail Wessex Region project encompasses full formation reconstruction, new track installation, and level crossing reinstatement.

Technical Specifications

Component Specification Standard
Track Length Site specific NR/L2/TRK/2102
Formation Depth 800mm minimum NR/L2/TRK/2102
Sleeper Type Concrete G44 NR/L2/TRK/2028
Rail Section CEN60 coated NR/L2/TRK/001
Crossing Surface Strail system NR/L3/TRK/3011

Implementation Timeline (Indicative only)

Phase Duration (hrs) Dependencies
Site Setup 2 Possession granted
Crossing Removal 4 Setup complete
Track Removal 3 Crossing clear
Formation Works 8 Track removed
Track Installation 6 Formation ready
Crossing Installation 4 Track complete

Technical Components

Track Renewal

Element Specification Implementation
Sleepers New concrete Full replacement
Rails Coated rails New installation
Formation Full dig Complete renewal
Track Bed New construction To standard

Level Crossing

Component Action Standard
Crossing Surface Removal/Reinstatement Network Rail spec
Foundations New installation Full depth
Drainage System renewal As required
Road Interface Full reconstruction Highway compliant

Work Sequence

  1. Crossing removal
  2. Track removal
  3. Formation excavation
  4. New formation construction
  5. New track installation
  6. Crossing reinstatement

Key Project Elements

. Formation Works:

  • Full depth excavation
  • New drainage installation
  • Engineered fill placement
  • Compaction to specification

. Track Installation:

  • New concrete sleepers
  • Coated rail sections
  • Pandrol fastening system
  • Stress-free installation

. Level Crossing:

  • New foundation system
  • Strail panel installation
  • Road interface works
  • Signal integration

. Quality Control:

  • Track geometry verification
  • Compaction testing
  • Rail stress measurements
  • Final inspection

More Info

 

 


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

By Possession Planning

Possession Planning is dedicated to providing news and insights for rail and road possession planning and delivery. Our mission is to serve as the premier information source for industry professionals managing critical infrastructure access, maintenance windows, and construction scheduling. Our Partners: FR2 Infrastructure | We Simplify Complexity | Construction Methodology | S | Energy Planning | Staging Diagrams . |

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading