Week 22-23 (9 Day Blockade) Track Renewal works at Crystal Palace Jnc

The VolkerRail Ltd Tonbridge Track Team as part of the Southern Renewals Enterprise completed the Track Renewal of 360/361/363A/B Pts. Works completed safely & ontime.

Electrification works completed:

☑️ 410m of New Conductor Rail
☑️ 140m of Serviceable 150lb/yd Conductor Rail Re-used
☑️ Over 950m of New Positive & Negative cable installed with 114 New cable lugs terminated utilising 18 Cable Management Sleepers
☑️ Modifications of 4 Existing Track Disconnectors which included a new 15m trough route & walkway
☑️ 12 New Conductor Rail Welds
☑️ Protection of a 20c Pilot Cable (CP to Norwood) adjacent to the excavation
☑️ Site Successfully Section Proved with Brighton ECR Monday 00:39 prior to possession handback
☑️ 1 New Points Heating Control Cubicle (Located on Platform 2)
☑️ 4 New Points Heating Transformers
☑️ 11 New TCB’s

Great work by all the Tonbridge team to deliver such a complex renewal.

More info

 

 

Tagged:

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading