3.4 Possession Request Minimum Pre-Requisites

The following shall be considered and included in the Possession Request:
• Type of track Possession to complete the scope of works (refer Section 2);
• Minimum time required to complete the work safely, allowing a reasonable amount of
contingency time;
• Significance / criticality of the works;
• Any handback windows to minimise train delays;
• Safe working limits required to conduct the works safely;
• Any impacts to signalling systems, ensuring that there are no impacts outside of the requested
possession limits;
• Any post-possession impacts that may be required after the Possession has been completed
e.g. Special train working or CAN warnings;
• Alignment, where relevant, with other works occurring on the same corridor or adjacent corridors
to minimise network disruption; and

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock