Budget at Completion (BAC)

Budget at Completion (BAC) – The sum of all budgets established for the work to be performed on a project or work breakdown structure component or schedule activity.

Key Characteristics:

  • Total authorized budget: Complete approved budget for the entire project
  • Performance measurement baseline: Key component of earned value management
  • Fixed reference point: Remains constant unless formally changed through change control
  • Excludes management reserve: Does not include funds held for unknown risks
  • Completion target: Represents planned total cost if project goes according to plan

BAC Components:

  • Direct costs: Labor, materials, equipment directly attributable to project work
  • Indirect costs: Overhead and administrative costs allocated to the project
  • Contingency reserves: Funds allocated for identified risks (known unknowns)
  • Profit/fee: If applicable in contracted projects

BAC Exclusions:

  • Management reserves: Funds for unknown risks (unknown unknowns)
  • Unallocated budget: Funds not yet assigned to specific work
  • Customer-furnished items: Resources provided by customer at no cost

Earned Value Management Role:
BAC is fundamental to all EVM calculations:

Key EVM Formulas Using BAC:

  • To-Complete Performance Index (TCPI): (BAC – EV) / (BAC – AC)
  • Variance at Completion (VAC): BAC – EAC
  • Percent Complete: EV / BAC × 100
  • Percent Spent: AC / BAC × 100

BAC vs. Related Budget Terms:

  • BAC: Total project budget (performance measurement baseline)
  • Project Budget: BAC + Management Reserves
  • EAC (Estimate at Completion): Forecasted final cost
  • ETC (Estimate to Complete): Remaining work cost estimate
  • TAB (Total Allocated Budget): BAC + Management Reserves

BAC Establishment Process:

  1. Cost estimation: Develop detailed project cost estimates
  2. Budget aggregation: Sum all work package and activity budgets
  3. Reserve allocation: Add contingency reserves for identified risks
  4. Time-phasing: Distribute BAC across project timeline (creates PV)
  5. Approval: Obtain formal authorization for BAC
  6. Baseline: Establish BAC as part of cost baseline

BAC Changes:

  • Change control required: BAC can only be modified through formal change management
  • Scope changes: Approved scope changes may alter BAC
  • Contract modifications: Changes to contracted work affect BAC
  • Re-baselining: Major changes may require complete baseline revision
  • Version control: Maintain history of BAC changes

Performance Analysis Using BAC:

Cost Performance:

  • Cost Variance (CV): EV – AC
  • Cost Performance Index (CPI): EV / AC
  • Variance at Completion (VAC): BAC – EAC

Schedule Performance:

  • Schedule Variance (SV): EV – PV
  • Schedule Performance Index (SPI): EV / PV

Completion Forecasting:

  • EAC = BAC / CPI (assumes future work at current efficiency)
  • EAC = AC + (BAC – EV) (assumes future work at planned efficiency)
  • EAC = AC + ETC (based on new estimate for remaining work)

BAC Applications:

  • Performance measurement: Compare actual progress against total budget
  • Forecasting: Predict final project costs relative to original budget
  • Variance analysis: Identify cost and schedule deviations
  • Change impact assessment: Evaluate effects of proposed changes
  • Stakeholder reporting: Communicate project financial status
  • Contract management: Track performance against contracted amounts

Example:
A software development project has:

  • Labor costs: $800,000
  • Hardware/software: $150,000
  • Contingency reserve: $50,000
  • BAC = $1,000,000

If at project midpoint:

  • EV = $600,000 (60% complete)
  • AC = $650,000 (actual spent)
  • CPI = 600,000 / 650,000 = 0.92
  • EAC = 1,000,000 / 0.92 = $1,087,000
  • VAC = 1,000,000 – 1,087,000 = -$87,000 (overrun)

Common Issues:

  • Unrealistic BAC: Overly optimistic budget setting
  • Scope creep: Work expansion without BAC adjustment
  • Poor estimation: Inadequate initial cost analysis
  • Change control gaps: Informal changes not reflected in BAC
  • Baseline integrity: Frequent changes undermining performance measurement

Best Practices:

  • Realistic budgeting: Base BAC on thorough cost analysis
  • Stakeholder agreement: Ensure all parties understand and accept BAC
  • Change discipline: Maintain strict change control over BAC
  • Regular monitoring: Track performance against BAC consistently
  • Clear documentation: Document BAC components and assumptions
  • Trend analysis: Monitor BAC performance trends over time

Reporting and Communication:

  • Budget status reports: Show spending against BAC
  • EVM reports: Display cost and schedule performance relative to BAC
  • Forecast reports: Project final costs compared to BAC
  • Variance reports: Highlight significant deviations from BAC
  • Dashboard metrics: Key performance indicators using BAC

Related Terms:

  • Estimate at Completion (EAC): Forecasted total project cost
  • Planned Value (PV): Time-phased portion of BAC
  • Earned Value (EV): Budgeted cost of completed work
  • Actual Cost (AC): Real cost incurred for completed work
  • Cost Baseline: Time-phased version of BAC
  • Management Reserve: Budget outside of BAC
  • Total Allocated Budget (TAB): BAC plus management reserves
  • Performance Measurement Baseline (PMB): Integrated scope-schedule-cost baseline including BAC
Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock