Rail Infrastructure: Critical Path Elements by Project Type

Rail Infrastructure: Critical Path Elements by Project Type

1. Track Reconditioning

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Track Assessment 2-4 weeks None N/A Access First activity
Material Procurement 8-12 weeks Assessment 6-8 weeks Supply After assessment
Possession Planning 4-6 weeks Assessment N/A Operations Before works
Rail Stressing During possession Temperature N/A Weather Last activity

2. Track Replacement

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Design Approval 12-16 weeks Survey N/A Stakeholders First activity
Rail Procurement 16-20 weeks Design 12-16 weeks Supply After design
OLE/Signaling Mods During possession Design 8-12 weeks Integration Before track works
Track Installation During possession All above N/A Weather Sequential activity

3. Ballast Cleaning

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Ground Investigation 4-6 weeks None N/A Conditions First activity
Machine Booking 12-16 weeks Planning N/A Availability Early booking required
Waste Management During works Planning 4-6 weeks Environment Continuous activity
Formation Works During possession Investigation N/A Ground conditions Before reinstatement

4. Station Upgrade

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Structural Assessment 8-12 weeks None N/A Hidden conditions First activity
Service Diversions 16-20 weeks Assessment 12 weeks Utilities Before construction
Platform Works 24-32 weeks Services N/A Operations Sequential stages
Systems Integration 12-16 weeks Construction 8 weeks Testing Final phase

5. New Stabling Yard

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Land Acquisition 24-52 weeks None N/A Legal First activity
Environmental Approval 20-30 weeks Concept N/A Approvals Before construction
Drainage/Services 16-24 weeks Approval 12 weeks Ground conditions Early works
OLE/Signaling 24-32 weeks Track works 16 weeks Integration Final systems

 6. Stabling Yard Upgrades

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Operational Assessment 6-8 weeks None N/A Service impact First activity
Power Upgrade 16-20 weeks Assessment 12 weeks Supply capacity Before new facilities
Track Modifications 12-16 weeks Design 8 weeks Operations Stage-dependent
Control Systems 20-24 weeks Power/Track 16 weeks Integration Final phase

7. Turntable Installation (Live Tracks)

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Ground Investigation 8-10 weeks None N/A Soil conditions First activity
Foundation Design 12-16 weeks Investigation N/A Approval Before procurement
Turntable Procurement 24-32 weeks Design 20 weeks Manufacturing Long lead item
Installation/Testing 6-8 weeks All above 4 weeks Integration Sequential commissioning

8. TBM Operations

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
TBM Procurement 40-52 weeks Design 36 weeks Manufacturing Critical first item
Launch Shaft 24-32 weeks Site prep 16 weeks Ground conditions Before TBM arrival
Segment Production Continuous Design 12 weeks Quality Ahead of TBM
Spoil Management During boring Planning 8 weeks Environmental Continuous activity

9. New Rail Lines

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Land Acquisition 52-104 weeks Planning N/A Legal/Social First major activity
Environmental Approval 40-52 weeks Initial design N/A Stakeholders Before construction
Bridge/Structures 52-78 weeks Approval 24 weeks Conditions Critical structures first
Systems Integration 32-40 weeks Civil works 24 weeks Interface Final phase

10. New Metro Lines

Critical Element Duration Dependencies Lead Time Key Risks Sequential Requirements
Tunnel Design 52-78 weeks Planning N/A Ground conditions First technical activity
Station Excavation 78-104 weeks Approval 24 weeks Utilities Critical path
Systems Design 52-78 weeks Civil design 32 weeks Integration Parallel to civil
Testing/Commissioning 32-40 weeks All works 16 weeks Certification Final phase

Resource Requirements Matrix

Project Type Key Equipment Specialist Staff Support Services Materials Logistics
Track Works Tampers/Regulators Track Engineers Survey teams Rails/Sleepers Just-in-time
Stations Cranes/Scaffolding Structural Engineers Security Construction Staged delivery
Stabling Heavy machinery Systems Engineers Utilities Track/OLE Bulk delivery
Tunneling TBM/Conveyors TBM crews Ventilation Segments Continuous
Metro Multiple TBMs Multi-discipline All services All types Complex

Interface Management

Interface Type Stakeholders Communication Frequency Documentation Risk Level
Operations Train operators Formal meetings Weekly Minutes/Actions High
Public Community Updates Monthly Newsletters Medium
Utilities Service providers Coordination Bi-weekly Agreements High
Emergency Services Planning Monthly Procedures Critical
Commercial Businesses Liaison As needed Records Medium
Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock