Rail Infrastructure: Critical Path Elements by Project Type
1. Track Reconditioning
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Track Assessment | 2-4 weeks | None | N/A | Access | First activity |
Material Procurement | 8-12 weeks | Assessment | 6-8 weeks | Supply | After assessment |
Possession Planning | 4-6 weeks | Assessment | N/A | Operations | Before works |
Rail Stressing | During possession | Temperature | N/A | Weather | Last activity |
2. Track Replacement
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Design Approval | 12-16 weeks | Survey | N/A | Stakeholders | First activity |
Rail Procurement | 16-20 weeks | Design | 12-16 weeks | Supply | After design |
OLE/Signaling Mods | During possession | Design | 8-12 weeks | Integration | Before track works |
Track Installation | During possession | All above | N/A | Weather | Sequential activity |
3. Ballast Cleaning
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Ground Investigation | 4-6 weeks | None | N/A | Conditions | First activity |
Machine Booking | 12-16 weeks | Planning | N/A | Availability | Early booking required |
Waste Management | During works | Planning | 4-6 weeks | Environment | Continuous activity |
Formation Works | During possession | Investigation | N/A | Ground conditions | Before reinstatement |
4. Station Upgrade
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Structural Assessment | 8-12 weeks | None | N/A | Hidden conditions | First activity |
Service Diversions | 16-20 weeks | Assessment | 12 weeks | Utilities | Before construction |
Platform Works | 24-32 weeks | Services | N/A | Operations | Sequential stages |
Systems Integration | 12-16 weeks | Construction | 8 weeks | Testing | Final phase |
5. New Stabling Yard
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Land Acquisition | 24-52 weeks | None | N/A | Legal | First activity |
Environmental Approval | 20-30 weeks | Concept | N/A | Approvals | Before construction |
Drainage/Services | 16-24 weeks | Approval | 12 weeks | Ground conditions | Early works |
OLE/Signaling | 24-32 weeks | Track works | 16 weeks | Integration | Final systems |
 6. Stabling Yard Upgrades
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Operational Assessment | 6-8 weeks | None | N/A | Service impact | First activity |
Power Upgrade | 16-20 weeks | Assessment | 12 weeks | Supply capacity | Before new facilities |
Track Modifications | 12-16 weeks | Design | 8 weeks | Operations | Stage-dependent |
Control Systems | 20-24 weeks | Power/Track | 16 weeks | Integration | Final phase |
7. Turntable Installation (Live Tracks)
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Ground Investigation | 8-10 weeks | None | N/A | Soil conditions | First activity |
Foundation Design | 12-16 weeks | Investigation | N/A | Approval | Before procurement |
Turntable Procurement | 24-32 weeks | Design | 20 weeks | Manufacturing | Long lead item |
Installation/Testing | 6-8 weeks | All above | 4 weeks | Integration | Sequential commissioning |
8. TBM Operations
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
TBM Procurement | 40-52 weeks | Design | 36 weeks | Manufacturing | Critical first item |
Launch Shaft | 24-32 weeks | Site prep | 16 weeks | Ground conditions | Before TBM arrival |
Segment Production | Continuous | Design | 12 weeks | Quality | Ahead of TBM |
Spoil Management | During boring | Planning | 8 weeks | Environmental | Continuous activity |
9. New Rail Lines
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Land Acquisition | 52-104 weeks | Planning | N/A | Legal/Social | First major activity |
Environmental Approval | 40-52 weeks | Initial design | N/A | Stakeholders | Before construction |
Bridge/Structures | 52-78 weeks | Approval | 24 weeks | Conditions | Critical structures first |
Systems Integration | 32-40 weeks | Civil works | 24 weeks | Interface | Final phase |
10. New Metro Lines
Critical Element | Duration | Dependencies | Lead Time | Key Risks | Sequential Requirements |
---|---|---|---|---|---|
Tunnel Design | 52-78 weeks | Planning | N/A | Ground conditions | First technical activity |
Station Excavation | 78-104 weeks | Approval | 24 weeks | Utilities | Critical path |
Systems Design | 52-78 weeks | Civil design | 32 weeks | Integration | Parallel to civil |
Testing/Commissioning | 32-40 weeks | All works | 16 weeks | Certification | Final phase |
Resource Requirements Matrix
Project Type | Key Equipment | Specialist Staff | Support Services | Materials | Logistics |
---|---|---|---|---|---|
Track Works | Tampers/Regulators | Track Engineers | Survey teams | Rails/Sleepers | Just-in-time |
Stations | Cranes/Scaffolding | Structural Engineers | Security | Construction | Staged delivery |
Stabling | Heavy machinery | Systems Engineers | Utilities | Track/OLE | Bulk delivery |
Tunneling | TBM/Conveyors | TBM crews | Ventilation | Segments | Continuous |
Metro | Multiple TBMs | Multi-discipline | All services | All types | Complex |
Interface Management
Interface Type | Stakeholders | Communication | Frequency | Documentation | Risk Level |
---|---|---|---|---|---|
Operations | Train operators | Formal meetings | Weekly | Minutes/Actions | High |
Public | Community | Updates | Monthly | Newsletters | Medium |
Utilities | Service providers | Coordination | Bi-weekly | Agreements | High |
Emergency | Services | Planning | Monthly | Procedures | Critical |
Commercial | Businesses | Liaison | As needed | Records | Medium |