UK – St John’s Footbridge, Rail-Based Installation Logistics

Force One Rail Division successfully supported the St John’s Footbridge project during a 26-hour possession, providing comprehensive rail logistics for bridge section transport and installation despite initial delays.

Equipment Deployment

Asset Quantity Application
RRVs 2 units Material transport
5m Trailers 3 units Component handling
7m Trailers 3 units Component handling
POS Package 1 set Operational safety
Quad-Fan Fleet Multiple units Support operations

Technical Implementation

Component Specification Challenge
Bridge Sections 26 tonnes total Heavy transport
Section Length 9-11 meters Oversized load
Transport Distance 1+ mile Track logistics
Track Complexity 14 point sets Navigation challenge
Construction Area Temporary setup Site preparation


More Info

 

Tagged:

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading