Force One Rail Division successfully supported the St John’s Footbridge project during a 26-hour possession, providing comprehensive rail logistics for bridge section transport and installation despite initial delays.
Equipment Deployment
| Asset | Quantity | Application |
|---|---|---|
| RRVs | 2 units | Material transport |
| 5m Trailers | 3 units | Component handling |
| 7m Trailers | 3 units | Component handling |
| POS Package | 1 set | Operational safety |
| Quad-Fan Fleet | Multiple units | Support operations |
Technical Implementation
| Component | Specification | Challenge |
|---|---|---|
| Bridge Sections | 26 tonnes total | Heavy transport |
| Section Length | 9-11 meters | Oversized load |
| Transport Distance | 1+ mile | Track logistics |
| Track Complexity | 14 point sets | Navigation challenge |
| Construction Area | Temporary setup | Site preparation |
Possession Planning is dedicated to providing news and insights for rail and road possession planning and delivery. Our mission is to serve as the premier information source for industry professionals managing critical infrastructure access, maintenance windows, and construction scheduling.
Our Partners: FR2 Infrastructure | We Simplify Complexity | Construction Methodology | S | Energy Planning | Staging Diagrams . |
Discover more from Possession Planning
Subscribe to get the latest posts sent to your email.