The Projects N&E Department has successfully completed a major signalling infrastructure upgrade during the Easter weekend possession, implementing significant system enhancements on the Navan branch line. The project included the commissioning of BEMU signalling enabling works and the extension of the DA01 interlocking boundary, representing a comprehensive modernization of rail control systems.

Installation Metrics

Component Quantity Specification
Containment 6 km System protection
Cable Installation 25 km Lineside & tail
Location Cases 12 units New installation
Axle Counters 47 units Train detection
Code Loops 5 units Signal control
VMS Signals 3 units Visual management

Technical Implementation

Element Scope Purpose
H Iron Sites Multiple locations Equipment support
UTX Installation Underground crossing Cable protection
System Integration Multi-component Operational control
Boundary Extension DA01 interlocking Coverage expansion
Testing Protocol Comprehensive System validation


More Info


Discover more from Possession Planning

Subscribe to get the latest posts sent to your email.

By Possession Planning

Possession Planning is dedicated to providing news and insights for rail and road possession planning and delivery. Our mission is to serve as the premier information source for industry professionals managing critical infrastructure access, maintenance windows, and construction scheduling. Our Partners: FR2 Infrastructure | We Simplify Complexity | Construction Methodology | S | Energy Planning | Staging Diagrams . |

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading