Sydney Metro West – Eastern Tunnelling Package Precast Production Completion

The Sydney Metro West – Eastern Tunnelling Package has reached a significant milestone with the completion of precast production. The journey began in 2024 at the Eastern Creek Precast Facility, where the first segment was cast. Since then, the dedicated team has worked tirelessly to produce over 16,000 high-quality segments.

Some key points about the project include:

  • The production of over 16,000 high-quality segments
  • The importance of starting strongly to ensure momentum when the TBMs got going
  • The team’s hard work and dedication to achieving this milestone

More info

 

 

Eastern Creek Precast Facility Opens Doors to Community

The Eastern Creek Precast Facility, a key player in the Sydney Metro West project, recently opened its doors to the community for a behind-the-scenes factory tour. The event was hosted by the Gamuda Australia and Laing O’Rourke Consortium, in collaboration with tunnelling contractors AFJV and JCGJV.

Some key points about the event include:

  • 320 community members attended the tour
  • The tour provided insight into the segment production process
  • Over 99,000 tunnelling segments have been produced at the facility so far
  • The segments will be used to line the 24-kilometre Sydney Metro West tunnels

More info

 

Tagged:

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading